Assessment Year | 2005 |
---|---|
Principal Product | Metal Plated Products |
NAICS | 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers |
SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 52 |
Plant Area |
69,500
ft2
|
Annual Production | 18,000,000
pieces
|
Production Hrs. Annual | 2,860
hrs
|
Location (State) | Ohio |
View Case Study |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $54,721 | 1,550,797 |
kWh
|
$0.035 |
Electricity Demand | $69,284 | 6,315 |
kW-mo/yr
|
$10.97 |
Electricity Fees | $2,407 | - |
|
- |
Natural Gas | $178,841 | 25,088 |
MMBtu
|
$7.13 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $28,931 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $22,875 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $6,011 | $1,797 | - | - |
$6,011
-
MMBtu
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,897 | $14,339 |
$2,533
71,818
kWh
|
$3,364
-
kW-mo/yr
|
- | - | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $5,386 | $1,840 |
$2,336
66,085
kWh
|
$3,050
-
kW-mo/yr
|
- | - | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $4,621 | $2,722 | - | - |
$4,621
-
MMBtu
|
- | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,818 | $1,000 | - | - |
$2,852
-
MMBtu
|
$(-34.0) | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,047 | $3,517 |
$455
12,876
kWh
|
$592
-
kW-mo/yr
|
- | - | - | |
07 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $780 | $1,076 |
$(-73.0)
(-2,051)
kWh
|
$(-186.0)
-
kW-mo/yr
|
$1,039
-
MMBtu
|
- | - | |
08 | 2.2628: Utilize a less expensive cooling method | $652 | $367 |
$279
8,045
kWh
|
$373
-
kW-mo/yr
|
- | - | - | |
09 | 2.4314: Use synthetic lubricant | $577 | $17 |
$248
7,032
kWh
|
$329
-
kW-mo/yr
|
- | - | - | |
10 | 2.4151: Develop a repair/replace policy | $459 | $54 |
$290
8,204
kWh
|
$373
-
kW-mo/yr
|
- | $(-204.0) | - | |
11 | 2.4231: Reduce the pressure of compressed air to the minimum required | $388 | $140 |
$300
8,572
kWh
|
$88
-
kW-mo/yr
|
- | - | - | |
12 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $295 | $180 |
$186
5,334
kWh
|
$241
-
kW-mo/yr
|
- | $(-102.0) | $(-30.0) | |
TOTAL RECOMMENDED | $28,931 | $27,049 |
$6,554
185,915
kWh
|
$8,224
-
kW-mo/yr
|
$14,523
-
MMBtu
|
$(-340.0) | $(-30.0) | ||
TOTAL IMPLEMENTED | $22,875 | $20,670 |
$5,799
164,467
kWh
|
$7,544
-
kW-mo/yr
|
$9,902
-
MMBtu
|
$(-340.0) | $(-30.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs