| Assessment Year | 2004 |
|---|---|
| Principal Product | Frozen Dough Products |
| NAICS | 311824: Dry Pasta, Dough, and Flour Mixes Manufacturing from Purchased Flour |
| SIC | 2045: Prepared Flour Mixes and Doughs |
| Sales Range | $10 M to 50M |
| # of Employees | 184 |
| Plant Area |
86,700
ft2
|
| Annual Production | 157,000,000
lb
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $397,604 | 19,984,034 |
kWh
|
$0.020 |
| Electricity Demand | $215,063 | 38,750 |
kW-mo/yr
|
$5.55 |
| Electricity Fees | $225,561 | - |
|
- |
| Natural Gas | $115,562 | 14,384 |
MMBtu
|
$8.03 |
| Fuel Oil #2 | $20,475 | 2,365 |
MMBtu
|
$8.66 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $79,980 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $73,966 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $30,817 | $4,062 |
$24,779
794,323
kWh
|
$6,038
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.2414: Use waste heat from hot flue gases to preheat | $15,918 | $4,120 | - | - |
$15,918
-
MMBtu
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,529 | $14,877 |
$5,703
182,772
kWh
|
$1,826
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4151: Develop a repair/replace policy | $6,476 | $360 |
$5,271
169,061
kWh
|
$1,565
-
kW-mo/yr
|
- | - | $(-360.0) | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,088 | $1,890 |
$3,044
97,569
kWh
|
$1,044
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.2437: Recover waste heat from equipment | $3,898 | $780 | - | - |
$3,898
-
MMBtu
|
- | - | |
| 07 | 2.2113: Repair or replace steam traps | $3,558 | $1,000 | - | - |
$4,638
-
MMBtu
|
- | $(-1,080.0) | |
| 08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,925 | $120 |
$2,257
72,371
kWh
|
$668
-
kW-mo/yr
|
- | - | - | |
| 09 | 3.6124: Burn waste oil for heat | $1,799 | $3,800 | - | - |
$1,624
-
MMBtu
|
$175
-
gal
|
- | |
| 10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,362 | $175 |
$1,051
33,839
kWh
|
$311
-
kW-mo/yr
|
- | - | - | |
| 11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,293 | - |
$1,005
32,314
kWh
|
$288
-
kW-mo/yr
|
- | - | - | |
| 12 | 2.2511: Insulate bare equipment | $317 | $117 | - | - |
$317
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $79,980 | $31,301 |
$43,110
1,382,249
kWh
|
$11,740
-
kW-mo/yr
|
$26,395
-
MMBtu
|
$175
-
gal
|
$(-1,440.0) | ||
| TOTAL IMPLEMENTED | $73,966 | $26,604 |
$43,110
1,382,249
kWh
|
$11,740
-
kW-mo/yr
|
$20,556
-
MMBtu
|
- | $(-1,440.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs