ITAC Assessment: WV0275
ITAC logo
ITAC Assessment: WV0275
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Precision fasteners
NAICS 332722: Bolt, Nut, Screw, Rivet, and Washer Manufacturing
SIC 3452: Bolts, Nuts, Screws, Rivets, and Washers
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 400,000
ft2
Annual Production 1,000,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $725,222 13,922,499
kWh
Electricity Demand $166,812 303,372
kW-mo/yr
Electricity Fees $221,454 -
Natural Gas $781,608 142,598
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $441,902 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $97,320

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.1321: Replace fossil fuel equipment with electrical equipment $277,857 $145,760 - - $292,857
-
MMBtu
$(-15,000.0)
02 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $29,059 $900 $26,430
388,811
kWh
$3,349
-
kW-mo/yr
- $(-720.0)
03 2.2437: Recover waste heat from equipment $16,752 $1,110 - - $16,752
-
MMBtu
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $16,337 $7,217 $14,348
211,041
kWh
$1,989
-
kW-mo/yr
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $16,308 - $14,322
210,672
kWh
$1,986
-
kW-mo/yr
- -
06 2.4239: Eliminate or reduce compressed air usage $13,654 $800 $11,992
176,400
kWh
$1,662
-
kW-mo/yr
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $13,244 $8,370 $10,139
149,194
kWh
$3,105
-
kW-mo/yr
- -
08 2.4231: Reduce the pressure of compressed air to the minimum required $13,170 $360 $11,566
170,233
kWh
$1,604
-
kW-mo/yr
- -
09 2.4221: Install compressor air intakes in coolest locations $12,345 $1,860 $10,841
159,557
kWh
$1,504
-
kW-mo/yr
- -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,549 $500 $8,386
123,323
kWh
$1,163
-
kW-mo/yr
- -
11 3.6124: Burn waste oil for heat $9,135 $3,600 - - $9,135
-
MMBtu
-
12 2.7111: Reduce illumination to minimum necessary levels $8,440 $1,200 $7,412
109,032
kWh
$1,028
-
kW-mo/yr
- -
13 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,716 $1,300 $3,264
47,996
kWh
$452
-
kW-mo/yr
- -
14 2.7135: Install occupancy sensors $2,336 $1,200 $2,052
30,179
kWh
$284
-
kW-mo/yr
- -
TOTAL RECOMMENDED $441,902 $174,177 $120,752
1,776,438
kWh
$18,126
-
kW-mo/yr
$318,744
-
MMBtu
$(-15,720.0)
TOTAL IMPLEMENTED $97,320 $12,130 $84,887
1,248,812
kWh
$13,153
-
kW-mo/yr
- $(-720.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs