ITAC Assessment: MUCM20
ITAC logo
ITAC Assessment: MUCM20
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Education
NAICS 611310: Colleges, Universities, and Professional Schools
SIC 8221: Colleges, Universities, and Professional Schools
Sales Range less than $500
k
# of Employees 100
Plant Area 75,348
ft2
Annual Production 100
units
Production Hrs. Annual 2,400
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $26,548 508,737
kWh
Electricity Demand $26,699 1,534
kW-mo/yr
Electricity Fees $2,700 -
Natural Gas $1,261 347
MMBtu
Other Energy $556 1
MMBtu
TOTAL YEARLY COSTS $57,764
RECOMMENDED SAVINGS* $7,024 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.6218: Turn off equipment when not in use $6,363 - $2,321
46,428
kWh
$4,042
-
kW-mo/yr
-
02 2.6218: Turn off equipment when not in use $318 $349 $216
4,310
kWh
$103
-
kW-mo/yr
-
03 2.7111: Reduce illumination to minimum necessary levels $124 - $28
555
kWh
$97
-
kW-mo/yr
-
04 2.7221: Lower temperature during the winter season and vice-versa $7 - $5
90
kWh
$2
-
kW-mo/yr
-
05 2.7492: Use proper thickness of insulation on building envelope $35 $124 $7
149
kWh
$13
-
kW-mo/yr
$15
-
MMBtu
06 3.1161: Eliminate/reduce an operation $178 - $120
2,398
kWh
$58
-
kW-mo/yr
-
TOTAL RECOMMENDED $7,024 $473 $2,696
53,930
kWh
$4,313
-
kW-mo/yr
$15
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs