Assessment Year | 2024 |
---|---|
Principal Product | Education |
NAICS | 611310: Colleges, Universities, and Professional Schools |
SIC | 8221: Colleges, Universities, and Professional Schools |
Sales Range | less than $500 k |
# of Employees | 100 |
Plant Area |
75,348
ft2
|
Annual Production | 100
units
|
Production Hrs. Annual | 2,400
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $26,548 | 508,737 |
kWh
|
$0.052 |
Electricity Demand | $26,699 | 1,534 |
kW-mo/yr
|
$17.41 |
Electricity Fees | $2,700 | - |
|
- |
Natural Gas | $1,261 | 347 |
MMBtu
|
$3.63 |
Other Energy | $556 | 1 |
MMBtu
|
$555.96 |
TOTAL YEARLY COSTS | $57,764 | |||
RECOMMENDED SAVINGS* | $7,024 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $6,363 | - |
$2,321
46,428
kWh
|
$4,042
-
kW-mo/yr
|
- | |
02 | 2.6218: Turn off equipment when not in use | $318 | $349 |
$216
4,310
kWh
|
$103
-
kW-mo/yr
|
- | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $124 | - |
$28
555
kWh
|
$97
-
kW-mo/yr
|
- | |
04 | 2.7221: Lower temperature during the winter season and vice-versa | $7 | - |
$5
90
kWh
|
$2
-
kW-mo/yr
|
- | |
05 | 2.7492: Use proper thickness of insulation on building envelope | $35 | $124 |
$7
149
kWh
|
$13
-
kW-mo/yr
|
$15
-
MMBtu
|
|
06 | 3.1161: Eliminate/reduce an operation | $178 | - |
$120
2,398
kWh
|
$58
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $7,024 | $473 |
$2,696
53,930
kWh
|
$4,313
-
kW-mo/yr
|
$15
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs