Assessment Year | 2003 |
---|---|
Principal Product | Open top plastic containers |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 275 |
Plant Area |
200,000
ft2
|
Annual Production | 6,000
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $711,831 | 15,038,881 |
kWh
|
$0.047 |
Electricity Fees | $5,697 | - |
|
- |
Natural Gas | $44,487 | 3,657 |
MMBtu
|
$12.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $179,959 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $118,222 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $76,401 | $2,253 |
$76,401
1,601,245
kWh
|
- | - | |
02 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $27,875 | $480 |
$28,547
612,370
kWh
|
- | $(-672.0) | |
03 | 2.7273: Install desiccant humidity control system | $36,152 | $180,000 |
$36,152
727,654
kWh
|
- | - | |
04 | 2.4239: Eliminate or reduce compressed air usage | $13,169 | $500 |
$13,169
275,940
kWh
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,764 | $128 |
$6,764
141,812
kWh
|
- | - | |
06 | 2.2625: Chill water to the highest temperature possible | $4,697 | $32 |
$4,697
98,448
kWh
|
- | - | |
07 | 2.2628: Utilize a less expensive cooling method | $3,967 | $1,741 |
$3,967
83,378
kWh
|
- | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $3,612 | $800 |
$3,612
75,728
kWh
|
- | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,425 | $250 |
$3,425
71,924
kWh
|
- | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,758 | - |
$2,758
57,816
kWh
|
- | - | |
11 | 2.7135: Install occupancy sensors | $839 | $800 |
$839
17,580
kWh
|
- | - | |
12 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $140 | $132 |
$140
2,930
kWh
|
- | - | |
13 | 3.1191: Change procedures / equipment / operating conditions | $160 | $32 | - |
$160
-
lb
|
- | |
TOTAL RECOMMENDED | $179,959 | $187,148 |
$180,471
3,766,825
kWh
|
$160
-
lb
|
$(-672.0) | ||
TOTAL IMPLEMENTED | $118,222 | $3,943 |
$118,734
2,502,747
kWh
|
$160
-
lb
|
$(-672.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs