Assessment Year | 2002 |
---|---|
Principal Product | Commercial Carpet |
NAICS |
n/a
|
SIC | 2273: Carpets and Rugs |
Sales Range | $100 M to 500M |
# of Employees | 800 |
Plant Area |
825,000
ft2
|
Annual Production | 126,000
thousand feet
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,353,664 | 30,494,639 |
kWh
|
$0.044 |
Natural Gas | $1,744,261 | 260,113 |
MMBtu
|
$6.71 |
Fuel Oil #2 | $23,666 | 3,204 |
MMBtu
|
$7.39 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $202,617 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,131 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1221: Replace obsolete burners with more efficient ones | $5,075 | - | - |
$4,788
-
MMBtu
|
- | $287 | - | - | |
02 | 2.2163: Use minimum steam operating pressure | $4,563 | - | - |
$4,305
-
MMBtu
|
- | $258 | - | - | |
03 | 2.2311: Heat treat parts only to required specifications or standards | $3,094 | - | - |
$2,919
-
MMBtu
|
- | $175 | - | - | |
04 | 2.8112: Combine utility meters | $5,560 | - | - | - | - | $5,560 | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,538 | - |
$3,338
46,449
kWh
|
- | - | $200 | - | - | |
06 | 3.4154: Eliminate leaks in water lines and valves | $140 | $330 |
$140
358
kWh
|
- | - | - | - | - | |
07 | 2.1231: Establish burner maintenance schedule for boilers | $12,802 | $1,500 | - |
$12,063
-
MMBtu
|
- | $739 | - | - | |
08 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $3,265 | $2,500 | - |
$3,080
-
MMBtu
|
- | $185 | - | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $3,091 | $3,500 |
$2,916
64,804
kWh
|
- | - | $175 | - | - | |
10 | 2.5111: Convert from indirect to direct fired systems | $29,536 | $16,300 | - |
$27,864
-
MMBtu
|
- | $1,672 | - | - | |
11 | 2.2514: Cover open tanks | $31,387 | $36,639 | - |
$29,610
-
MMBtu
|
- | $1,777 | - | - | |
12 | 2.5191: Modify dye beck | $22,904 | $73,150 | - |
$21,154
-
MMBtu
|
- | $1,269 | $320 |
$161
-
Tgal
|
|
13 | 3.1191: Change procedures / equipment / operating conditions | $77,662 | $80,000 | - | - |
$2,906
-
lb
|
- | $74,756 | - | |
TOTAL RECOMMENDED | $202,617 | $213,919 |
$6,394
111,611
kWh
|
$105,783
-
MMBtu
|
$2,906
-
lb
|
$12,297 | $75,076 |
$161
-
Tgal
|
||
TOTAL IMPLEMENTED | $17,131 | $6,330 |
$3,056
65,162
kWh
|
$7,868
-
MMBtu
|
- | $6,207 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs