Assessment Year | 2003 |
---|---|
Principal Product | Apple juice and apple sauce |
NAICS | 311421: Fruit and Vegetable Canning |
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
305,775
ft2
|
Annual Production | 2,500,000
pieces
|
Production Hrs. Annual | 4,200
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $107,646 | 4,236,920 |
kWh
|
$0.025 |
Electricity Demand | $88,128 | 9,476 |
kW-mo/yr
|
$9.30 |
Natural Gas | $18,953 | 1,973 |
MMBtu
|
$9.61 |
LPG | $152,698 | 58,976 |
MMBtu
|
$2.59 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $100,770 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $33,380 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $1,233 | $659 | - | - | - |
$1,233
-
MMBtu
|
- | - | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $29,173 | $3,000 | - | - | - |
$29,173
-
MMBtu
|
- | - | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $14,048 | $1,000 | - | - | - |
$14,048
-
MMBtu
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $339 | - |
$174
8,845
kWh
|
$165
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,273 | - |
$1,711
87,061
kWh
|
$1,562
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,584 | - |
$1,302
66,218
kWh
|
$1,282
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.2437: Recover waste heat from equipment | $1,748 | $240 | - | - | - |
$1,748
-
MMBtu
|
- | - | |
08 | 2.7111: Reduce illumination to minimum necessary levels | $786 | - |
$305
15,529
kWh
|
$481
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $889 | - |
$378
19,338
kWh
|
$511
-
kW-mo/yr
|
- | - | - | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,757 | $4,080 |
$1,158
58,966
kWh
|
$1,599
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.4239: Eliminate or reduce compressed air usage | $2,878 | $160 |
$1,204
61,219
kWh
|
$1,674
-
kW-mo/yr
|
- | - | - | - | |
12 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $4,116 | - |
$2,095
106,359
kWh
|
$2,489
-
kW-mo/yr
|
- | - | - | $(-468.0) | |
13 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $676 | $300 |
$288
6,153
kWh
|
$388
-
kW-mo/yr
|
- | - | - | - | |
14 | 2.2113: Repair or replace steam traps | $3,018 | $1,000 | - | - |
$3,018
-
MMBtu
|
- | - | - | |
15 | 3.4151: Minimize water usage | $33,252 | $9,000 | - | - | - |
$18,358
-
MMBtu
|
$14,894
-
Tgal
|
- | |
TOTAL RECOMMENDED | $100,770 | $19,439 |
$8,615
429,688
kWh
|
$10,151
-
kW-mo/yr
|
$3,018
-
MMBtu
|
$64,560
-
MMBtu
|
$14,894
-
Tgal
|
$(-468.0) | ||
TOTAL IMPLEMENTED | $33,380 | $7,039 |
$7,237
359,624
kWh
|
$8,312
-
kW-mo/yr
|
$3,018
-
MMBtu
|
$15,281
-
MMBtu
|
- | $(-468.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs