Assessment Year | 2013 |
---|---|
Principal Product | Lithium Ion Cells, Modules, Packs, Systems and Battery Management |
NAICS | 335912: Primary Battery Manufacturing |
SIC | 3692: Primary Batteries, Dry and Wet |
Sales Range | $10 M to 50M |
# of Employees | 48 |
Plant Area |
65,883
ft2
|
Annual Production | 615
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $220,638 | 8,232,750 |
kWh
|
$0.027 |
Electricity Demand | $170,586 | 16,757 |
kW-mo/yr
|
$10.18 |
Natural Gas | $133,702 | 18,145 |
MMBtu
|
$7.37 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $41,417 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,803 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $25,849 | - | - | - | $19,186 | - | $6,663 | |
02 | 2.7221: Lower temperature during the winter season and vice-versa | $3,997 | - | - | - | - |
$3,997
-
MMBtu
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,183 | - |
$666
24,849
kWh
|
$1,517
-
kW-mo/yr
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,360 | - |
$1,360
50,742
kWh
|
- | - | - | - | |
05 | 2.6218: Turn off equipment when not in use | $263 | - |
$263
9,806
kWh
|
- | - | - | - | |
06 | 2.7135: Install occupancy sensors | $1,409 | $58 |
$1,409
52,559
kWh
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,703 | $2,128 |
$1,739
64,900
kWh
|
$3,964
-
kW-mo/yr
|
- | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $653 | $1,081 |
$199
7,440
kWh
|
$454
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $41,417 | $3,267 |
$5,636
210,296
kWh
|
$5,935
-
kW-mo/yr
|
$19,186 |
$3,997
-
MMBtu
|
$6,663 | ||
TOTAL IMPLEMENTED | $7,803 | - |
$2,289
85,397
kWh
|
$1,517
-
kW-mo/yr
|
- |
$3,997
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs