| Assessment Year | 2003 |
|---|---|
| Principal Product | Apple juice and apple sauce |
| NAICS | 311421: Fruit and Vegetable Canning |
| SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
289,874
ft2
|
| Annual Production | 530
units
|
| Production Hrs. Annual | 1,955
hrs
|
| Location (State) | West Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $183,961 | 3,070,673 |
kWh
|
$0.060 |
| Natural Gas | $12,064 | 1,591 |
MMBtu
|
$7.58 |
| LPG | $470,880 | 156,427 |
MMBtu
|
$3.01 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $77,786 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,348 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | LPG Savings | Water Disposal Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $876 | $130 |
$876
14,633
kWh
|
- | - | - | - | |
| 02 | 2.2437: Recover waste heat from equipment | $1,475 | $198 | - |
$1,475
-
MMBtu
|
- | - | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $456 | $250 |
$456
7,618
kWh
|
- | - | - | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $597 | $52 |
$597
106,652
kWh
|
- | - | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,293 | $4,594 |
$1,293
21,589
kWh
|
- | - | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $534 | - |
$534
8,917
kWh
|
- | - | - | - | |
| 07 | 2.7111: Reduce illumination to minimum necessary levels | $1,720 | $400 |
$1,720
28,714
kWh
|
- | - | - | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $175 | - |
$175
528
kWh
|
- | - | - | - | |
| 09 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $1,444 | $130 |
$1,600
26,663
kWh
|
- | - | - | $(-156.0) | |
| 10 | 2.2162: Reduce excess steam bleeding | $15,707 | $60,000 |
$15,707
242,018
kWh
|
- | - | - | - | |
| 11 | 3.4151: Minimize water usage | $26,493 | $6,000 | - | - |
$19,676
-
MMBtu
|
$6,817
-
Tgal
|
- | |
| 12 | 2.2135: Repair and eliminate steam leaks | $411 | $1,000 | - | - |
$364
-
MMBtu
|
$47
-
Tgal
|
- | |
| 13 | 2.4239: Eliminate or reduce compressed air usage | $298 | $40 |
$298
4,927
kWh
|
- | - | - | - | |
| 14 | 2.2414: Use waste heat from hot flue gases to preheat | $26,307 | $1,855 | - | - |
$26,307
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $77,786 | $74,649 |
$23,256
462,259
kWh
|
$1,475
-
MMBtu
|
$46,347
-
MMBtu
|
$6,864
-
Tgal
|
$(-156.0) | ||
| TOTAL IMPLEMENTED | $7,348 | $6,346 |
$7,093
212,623
kWh
|
- |
$364
-
MMBtu
|
$47
-
Tgal
|
$(-156.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | LPG Savings | Water Disposal Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs