ITAC Assessment: WV0250
ITAC logo
ITAC Assessment: WV0250
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Furniture grade lumber
NAICS
n/a
SIC 2491: Wood Preserving
Sales Range $5
M
to 10
M
# of Employees 54
Plant Area 60,000
ft2
Annual Production 13,000
thousand feet
Production Hrs. Annual 4,000
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $118,971 2,185,920
kWh
Natural Gas $106,824 15,944
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $118,584 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,467

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.4221: Install compressor air intakes in coolest locations $718 $230 $718
13,081
kWh
- - - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,500 - $4,500
82,626
kWh
- - - -
03 2.1233: Analyze flue gas for proper air/fuel ratio $2,399 $1,000 - $2,399
-
MMBtu
- - -
04 2.7111: Reduce illumination to minimum necessary levels $765 $30 $765
14,080
kWh
- - - -
05 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $4,266 $300 $4,626
84,970
kWh
- - $(-360.0) -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $150 - $150
4,576
kWh
- - - -
07 2.2511: Insulate bare equipment $1,387 $188 - $1,387
-
MMBtu
- - -
08 2.1224: Replace boiler $65,563 $100,000 - $65,563
-
MMBtu
- - -
09 2.4231: Reduce the pressure of compressed air to the minimum required $5,056 $3,735 $5,056
92,881
kWh
- - - -
10 3.6193: Install equipment (eg compactor) to reduce disposal costs $900 $665 - - $900
-
gal
- -
11 4.632: Change operating conditions $21,375 $875 - - - - $21,375
12 4.126: Install sensors to detect defects $11,505 $13,600 - - - - $11,505
TOTAL RECOMMENDED $118,584 $120,623 $15,815
292,214
kWh
$69,349
-
MMBtu
$900
-
gal
$(-360.0) $32,880
TOTAL IMPLEMENTED $13,467 $1,518 $10,041
186,252
kWh
$3,786
-
MMBtu
- $(-360.0) -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs