Assessment Year | 2002 |
---|---|
Principal Product | Canned milk and juices |
NAICS |
n/a
|
SIC | 2026: Fluid Milk |
Sales Range | $10 M to 50M |
# of Employees | 42 |
Plant Area |
76,550
ft2
|
Annual Production | 20,800
Tgal
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $267,151 | 4,414,714 |
kWh
|
$0.061 |
Natural Gas | $5,165 | 814 |
MMBtu
|
$6.35 |
Fuel Oil #2 | $54,350 | 9,755 |
MMBtu
|
$5.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $30,593 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,496 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $656 | $600 |
$656
10,527
kWh
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $249 | - |
$249
3,997
kWh
|
- | - | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,539 | - |
$4,539
75,008
kWh
|
- | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,277 | $240 |
$1,277
21,096
kWh
|
- | - | - | - | |
05 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $5,200 | $400 |
$5,680
93,760
kWh
|
- | - | $(-480.0) | - | |
06 | 2.2414: Use waste heat from hot flue gases to preheat | $5,264 | $2,255 | - |
$5,264
-
MMBtu
|
- | - | - | |
07 | 2.7144: Install spectral reflectors / delamp | $621 | $1,140 |
$621
10,108
kWh
|
- | - | - | - | |
08 | 2.4235: Remove or close off unneeded compressed air lines | $787 | $1,300 |
$787
13,015
kWh
|
- | - | - | - | |
09 | 2.2511: Insulate bare equipment | $3,472 | $2,563 |
$2,074
34,281
kWh
|
$1,398
-
MMBtu
|
- | - | - | |
10 | 3.4156: Use flow control valves on equipment to optimize water use | $458 | $830 | - | - |
$458
-
Tgal
|
- | - | |
11 | 3.4115: Recover and reuse cooling water | $5,769 | $5,000 | - | - |
$5,769
-
Tgal
|
- | - | |
12 | 4.821: Pay bills on time to avoid late fees | $2,301 | - | - | - | - | - | $2,301 | |
TOTAL RECOMMENDED | $30,593 | $14,328 |
$15,883
261,792
kWh
|
$6,662
-
MMBtu
|
$6,227
-
Tgal
|
$(-480.0) | $2,301 | ||
TOTAL IMPLEMENTED | $17,496 | $4,033 |
$13,819
228,142
kWh
|
$1,398
-
MMBtu
|
$458
-
Tgal
|
$(-480.0) | $2,301 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs