| Assessment Year | 2002 |
|---|---|
| Principal Product | Kiln dried lumber |
| NAICS |
n/a
|
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | $5 M to 10M |
| # of Employees | 165 |
| Plant Area |
40,000
ft2
|
| Annual Production | 400,000
thousand feet
|
| Production Hrs. Annual | 2,550
hrs
|
| Location (State) | West Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $541,199 | 11,469,248 |
kWh
|
$0.047 |
| Wood | $12,750 | 45,109 |
MMBtu
|
$0.28 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $187,829 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $25,310 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Wood Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,167 | - |
$3,167
67,097
kWh
|
- | - | - | - | |
| 02 | 2.2414: Use waste heat from hot flue gases to preheat | $611 | $1,695 | - |
$611
-
MMBtu
|
- | - | - | |
| 03 | 2.2628: Utilize a less expensive cooling method | $7,620 | $4,870 |
$7,620
161,443
kWh
|
- | - | - | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $871 | $116 |
$871
18,447
kWh
|
- | - | - | - | |
| 05 | 2.2437: Recover waste heat from equipment | $4,564 | $128 |
$4,564
211,751
kWh
|
- | - | - | - | |
| 06 | 2.7111: Reduce illumination to minimum necessary levels | $456 | $72 |
$456
9,509
kWh
|
- | - | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $304 | - |
$304
6,420
kWh
|
- | - | - | - | |
| 08 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $8,335 | $900 |
$8,623
182,539
kWh
|
- | - | $(-288.0) | - | |
| 09 | 3.6124: Burn waste oil for heat | $5,537 | $4,000 | - | - |
$5,537
-
lb
|
- | - | |
| 10 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $864 | $400 | - | - |
$864
-
lb
|
- | - | |
| 11 | 4.126: Install sensors to detect defects | $127,500 | $13,480 | - | - | - | - | $127,500 | |
| 12 | 4.652: Replace existing equipment with more suitable substitutes | $28,000 | $12,000 | - | - | - | - | $28,000 | |
| TOTAL RECOMMENDED | $187,829 | $37,661 |
$25,605
657,206
kWh
|
$611
-
MMBtu
|
$6,401
-
lb
|
$(-288.0) | $155,500 | ||
| TOTAL IMPLEMENTED | $25,310 | $6,370 |
$24,734
638,759
kWh
|
- |
$864
-
lb
|
$(-288.0) | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Wood Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs