Assessment Year | 2002 |
---|---|
Principal Product | Machinery for Rubber Industry |
NAICS |
n/a
|
SIC | 3553: Woodworking Machinery |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
295,000
ft2
|
Annual Production | 4,000
pieces
|
Production Hrs. Annual | 4,125
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $158,028 | 3,220,107 |
kWh
|
$0.049 |
Electricity Demand | $59,281 | 9,044 |
kW-mo/yr
|
$6.55 |
Natural Gas | $277,323 | 35,567 |
MMBtu
|
$7.80 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $133,973 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $80,412 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $1,256 | $450 |
$906
18,459
kWh
|
$350
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,302 | $26,610 |
$6,529
132,949
kWh
|
$2,773
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.2511: Insulate bare equipment | $213 | $163 | - | - |
$213
-
MMBtu
|
- | - | - | - | |
04 | 2.2628: Utilize a less expensive cooling method | $123 | $86 |
$89
1,817
kWh
|
$34
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $500 | $248 |
$315
6,416
kWh
|
$185
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.2515: Use optimum thickness insulation | $21,621 | $9,375 | - | - |
$21,621
-
MMBtu
|
- | - | - | - | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $18,364 | $1,500 |
$12,928
263,407
kWh
|
$5,436
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $8,531 | $1,500 |
$6,422
130,971
kWh
|
$2,469
-
kW-mo/yr
|
- | - | $(-360.0) | - | - | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,763 | - |
$1,984
40,418
kWh
|
$779
-
kW-mo/yr
|
- | - | - | - | - | |
10 | 3.5316: Contract a wood pallet recycling company | $360 | $100 | - | - | - |
$360
-
lb
|
- | - | - | |
11 | 4.521: Clear and rent existing space | $39,500 | $2,700 | - | - | - | - | - | $39,500 | - | |
12 | 4.425: Eliminate/reduce redundant inspections | $12,000 | $3,228 | - | - | - | - | - | - | $12,000 | |
13 | 4.132: Purchase new equipment to reduce material use / cost | $19,440 | $6,060 | - | - | - | - | - | - | $19,440 | |
TOTAL RECOMMENDED | $133,973 | $52,020 |
$29,173
594,437
kWh
|
$12,026
-
kW-mo/yr
|
$21,834
-
MMBtu
|
$360
-
lb
|
$(-360.0) | $39,500 | $31,440 | ||
TOTAL IMPLEMENTED | $80,412 | $33,109 |
$28,858
588,021
kWh
|
$11,841
-
kW-mo/yr
|
$213
-
MMBtu
|
$360
-
lb
|
$(-360.0) | $39,500 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs