ITAC Assessment: WV0238
ITAC logo
ITAC Assessment: WV0238
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Welded Assembly for Automobiles
NAICS
n/a
SIC 3544: Special Dies and Tools, Die Sets, Jigs and Fixtures, and Industrial Molds
Sales Range $50
M
to 100
M
# of Employees 200
Plant Area 50,000
ft2
Annual Production 45,900
pieces
Production Hrs. Annual 4,340
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $100,541 1,912,480
kWh
Electricity Demand $22,291 4,200
kW-mo/yr
Natural Gas $936 85
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $42,925 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,778

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Water Consumption Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,740 $100 $2,307
44,185
kWh
$433
-
kW-mo/yr
- - - -
02 2.2625: Chill water to the highest temperature possible $424 $60 $323
6,187
kWh
$101
-
kW-mo/yr
- - - -
03 2.4221: Install compressor air intakes in coolest locations $1,462 $188 $1,232
23,396
kWh
$230
-
kW-mo/yr
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,250 $315 $1,710
32,634
kWh
$540
-
kW-mo/yr
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,894 $2,910 $1,232
23,291
kWh
$662
-
kW-mo/yr
- - - -
06 2.4226: Use / purchase optimum sized compressor $5,806 - $3,742
71,658
kWh
$2,064
-
kW-mo/yr
- - - -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $649 $450 $493
9,376
kWh
$156
-
kW-mo/yr
- - - -
08 2.7221: Lower temperature during the winter season and vice-versa $4,813 - $2,941
55,963
kWh
$1,872
-
kW-mo/yr
- - - -
09 2.2692: Use outside cold water source as a supply of cooling water $6,165 - $5,421
103,118
kWh
$1,728
-
kW-mo/yr
- - - $(-984.0)
-
Tgal
10 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $1,562 $150 $1,324
25,198
kWh
$418
-
kW-mo/yr
- $(-180.0) - -
11 3.5317: Sell / offer by-product as animal feed $2,080 $100 - - $2,080
-
lb
- - -
12 3.5316: Contract a wood pallet recycling company $1,560 $100 - - $1,560
-
lb
- - -
13 4.621: Use fixtures to reduce machine changeout times $11,520 $1,620 - - - - $11,520 -
TOTAL RECOMMENDED $42,925 $5,993 $20,725
395,006
kWh
$8,204
-
kW-mo/yr
$3,640
-
lb
$(-180.0) $11,520 $(-984.0)
-
Tgal
TOTAL IMPLEMENTED $23,778 $4,185 $14,072
268,492
kWh
$6,246
-
kW-mo/yr
$3,640
-
lb
$(-180.0) - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs