| Assessment Year | 2023 |
|---|---|
| Principal Product | Filters |
| NAICS | 333413: Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing |
| SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
| Sales Range | $50 M to 100M |
| # of Employees | 430 |
| Plant Area |
350,000
ft2
|
| Annual Production | 4,160,000
pieces
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $142,863 | 4,829,025 |
kWh
|
$0.030 |
| Electricity Demand | $236,162 | 9,823 |
kW-mo/yr
|
$24.04 |
| Electricity Fees | $69,358 | - |
|
- |
| Natural Gas | $24,739 | 1,502 |
MMBtu
|
$16.47 |
| TOTAL YEARLY COSTS | $473,122 | |||
| RECOMMENDED SAVINGS* | $129,561 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,411 | $30,977 |
$8,227
278,098
kWh
|
$9,184
-
kW-mo/yr
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,325 | $2,880 |
$3,325
110,827
kWh
|
- | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,566 | - |
$1,566
52,911
kWh
|
- | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,515 | $14,625 |
$4,515
152,545
kWh
|
- | |
| 05 | 2.9114: Use solar heat to make electricty | $95,755 | $917,406 |
$38,527
1,302,269
kWh
|
$57,228
-
kW-mo/yr
|
|
| 06 | 2.7243: Improve air circulation with destratification fans / other methods | $6,989 | $15,000 |
$6,989
236,229
kWh
|
- | |
| TOTAL RECOMMENDED | $129,561 | $980,888 |
$63,149
2,132,879
kWh
|
$66,412
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs