ITAC Assessment: WV0217
ITAC logo
ITAC Assessment: WV0217
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product wooden pallets and pallet parts
NAICS
n/a
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 89
Plant Area 81,000
ft2
Annual Production 12,000
thousand feet
Production Hrs. Annual 4,500
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $199,587 3,120,018
kWh
Natural Gas $8,888 1,320
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $197,431 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $40,870

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $10,319 $1,925 $10,319
156,169
kWh
- -
02 2.6212: Turn off equipment during breaks, reduce operating time $2,187 - - $2,187
-
MMBtu
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,084 $54 $1,084
16,408
kWh
- -
04 2.7111: Reduce illumination to minimum necessary levels $1,646 $162 $1,646
24,905
kWh
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,433 $68 $1,433
21,682
kWh
- -
06 2.4157: Establish a predictive maintenance program $8,151 $270 $8,151
125,697
kWh
- -
07 3.6123: Burn wood by-products for heat $136,561 $325,000 $136,561
1,565,499
kWh
- -
08 4.323: Optimize lot sizes to reduce inventory carrying costs $16,050 $15,248 - - $16,050
09 4.652: Replace existing equipment with more suitable substitutes $20,000 $30,000 - - $20,000
TOTAL RECOMMENDED $197,431 $372,727 $159,194
1,910,360
kWh
$2,187
-
MMBtu
$36,050
TOTAL IMPLEMENTED $40,870 $17,727 $22,633
344,861
kWh
$2,187
-
MMBtu
$16,050
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs