Assessment Year | 2001 |
---|---|
Principal Product | Rough Lumber |
NAICS |
n/a
|
SIC | 3531: Construction Machinery and Equipment |
Sales Range | $5 M to 10M |
# of Employees | 90 |
Plant Area |
23,150
ft2
|
Annual Production | 20,000
thousand feet
|
Production Hrs. Annual | 4,590
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $110,605 | 3,962,400 |
kWh
|
$0.028 |
Electricity Demand | $84,793 | 794 |
kW-mo/yr
|
$106.79 |
Wood | $28,688 | 67,664 |
MMBtu
|
$0.42 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $124,051 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $32,592 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Wood Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,402 | $40 |
$2,402
50,103
kWh
|
- | - | - | - | |
02 | 2.2113: Repair or replace steam traps | $1,680 | $2,680 | - |
$1,680
-
MMBtu
|
- | - | - | |
03 | 2.2511: Insulate bare equipment | $555 | $588 | - |
$555
-
MMBtu
|
- | - | - | |
04 | 2.3414: Burn waste to produce steam to drive a steam turbine generator set and use steam exhaust for heat | $52,028 | $185,000 |
$52,028
2,147,104
kWh
|
- | - | - | - | |
05 | 2.7135: Install occupancy sensors | $659 | $150 |
$659
17,287
kWh
|
- | - | - | - | |
06 | 2.4157: Establish a predictive maintenance program | $7,955 | $1,500 |
$7,955
170,819
kWh
|
- | - | - | - | |
07 | 3.5313: Increase amount of waste recovered for resale | $35,000 | $1,500 | - | - | - |
$35,000
-
lb
|
- | |
08 | 3.6124: Burn waste oil for heat | $3,772 | $5,000 | - | - |
$3,772
-
gal
|
- | - | |
09 | 4.652: Replace existing equipment with more suitable substitutes | $20,000 | $7,000 | - | - | - | - | $20,000 | |
TOTAL RECOMMENDED | $124,051 | $203,458 |
$63,044
2,385,313
kWh
|
$2,235
-
MMBtu
|
$3,772
-
gal
|
$35,000
-
lb
|
$20,000 | ||
TOTAL IMPLEMENTED | $32,592 | $11,808 |
$10,357
220,922
kWh
|
$2,235
-
MMBtu
|
- | - | $20,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Wood Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs