Assessment Year | 2000 |
---|---|
Principal Product | Potato Chips |
NAICS |
n/a
|
SIC | 2096: Potato Chips, Corn Chips, and Similar Snacks |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
180,950
ft2
|
Annual Production | 16,500,000
lb
|
Production Hrs. Annual | 6,732
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $99,750 | 3,850,528 |
kWh
|
$0.026 |
Electricity Demand | $121,659 | 8,932 |
kW-mo/yr
|
$13.62 |
Natural Gas | $349,672 | 75,067 |
MMBtu
|
$4.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $272,873 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $45,380 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,112 | $25 |
$3,112
120,164
kWh
|
- | - | - | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $35,579 | $8,440 | - |
$35,579
-
MMBtu
|
- | - | |
03 | 2.4314: Use synthetic lubricant | $1,587 | $727 |
$1,587
61,254
kWh
|
- | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $471 | $500 |
$471
18,171
kWh
|
- | - | - | |
05 | 2.4157: Establish a predictive maintenance program | $2,070 | $1,012 |
$2,070
41,032
kWh
|
- | - | - | |
06 | 2.2511: Insulate bare equipment | $3,609 | $636 | - |
$3,609
-
MMBtu
|
- | - | |
07 | 2.7135: Install occupancy sensors | $615 | $500 |
$615
23,740
kWh
|
- | - | - | |
08 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $32,382 | $4,822 | - |
$32,382
-
MMBtu
|
- | - | |
09 | 2.8114: Change rate schedules or other changes in utility service | $34,531 | - | - |
$34,531
-
MMBtu
|
- | - | |
10 | 3.6126: Direct waste gasses to boiler combustion air | $56,401 | $150,000 | - | - |
$56,401
-
lb
|
- | |
11 | 4.441: Install automatic packing equipment | $87,516 | $120,000 | - | - | - | $87,516 | |
12 | 4.424: Improve space comfort conditioning | $15,000 | $901 | - | - | - | $15,000 | |
TOTAL RECOMMENDED | $272,873 | $287,563 |
$7,855
264,361
kWh
|
$106,101
-
MMBtu
|
$56,401
-
lb
|
$102,516 | ||
TOTAL IMPLEMENTED | $45,380 | $2,900 |
$7,240
240,621
kWh
|
$38,140
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs