Assessment Year | 2000 |
---|---|
Principal Product | Automotive parts |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
150,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,056
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $109,840 | 1,883,939 |
kWh
|
$0.058 |
Natural Gas | $48,381 | 5,349 |
MMBtu
|
$9.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $55,806 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $25,749 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7145: Install skylights | $734 | $3,000 |
$734
12,603
kWh
|
- | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $683 | $240 |
$683
11,723
kWh
|
- | - | - | - | |
03 | 2.7231: Use radiant heater for spot heating | $5,858 | $6,900 | - |
$5,858
-
MMBtu
|
- | - | - | |
04 | 2.4314: Use synthetic lubricant | $397 | $417 |
$397
6,741
kWh
|
- | - | - | - | |
05 | 2.7144: Install spectral reflectors / delamp | $4,368 | $4,872 |
$4,368
74,736
kWh
|
- | - | - | - | |
06 | 2.7135: Install occupancy sensors | $3,368 | $400 |
$3,368
57,737
kWh
|
- | - | - | - | |
07 | 2.8114: Change rate schedules or other changes in utility service | $13,587 | $200 | - |
$13,587
-
MMBtu
|
- | - | - | |
08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $12,960 | $800 | - | - | - |
$12,960
-
lb
|
- | |
09 | 3.4111: Use closed cycle process to minimize waste water production | $5,851 | $1,850 | - | - |
$5,851
-
Tgal
|
- | - | |
10 | 4.521: Clear and rent existing space | $8,000 | $500 | - | - | - | - | $8,000 | |
TOTAL RECOMMENDED | $55,806 | $19,179 |
$9,550
163,540
kWh
|
$19,445
-
MMBtu
|
$5,851
-
Tgal
|
$12,960
-
lb
|
$8,000 | ||
TOTAL IMPLEMENTED | $25,749 | $10,207 |
$1,080
18,464
kWh
|
$5,858
-
MMBtu
|
$5,851
-
Tgal
|
$12,960
-
lb
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs