Assessment Year | 2000 |
---|---|
Principal Product | Laminated Wood |
NAICS |
n/a
|
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $100 M to 500M |
# of Employees | 320 |
Plant Area |
360,000
ft2
|
Annual Production | 5,000
thousand feet
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,808,501 | 46,726,847 |
kWh
|
$0.039 |
Electricity Demand | $693,115 | 97,762 |
kW-mo/yr
|
$7.09 |
Electricity Fees | $39,105 | - |
|
- |
Natural Gas | $313,911 | 91,018 |
MMBtu
|
$3.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $349,857 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $87,417 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $6,707 | $280 | - |
$6,707
-
MMBtu
|
- | - | |
02 | 2.7314: Reduce ventilation air | $694 | $1,170 | - |
$694
-
MMBtu
|
- | - | |
03 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $33,886 | $10,000 | - |
$33,886
-
MMBtu
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $2,156 | $220 |
$2,156
90,270
kWh
|
- | - | - | |
05 | 4.821: Pay bills on time to avoid late fees | $40,958 | $200 | - |
$40,958
-
MMBtu
|
- | - | |
06 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $4,706 | $870 | - | - |
$4,706
-
lb
|
- | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,710 | $11,000 | - | - |
$3,710
-
lb
|
- | |
08 | 4.445: Install equipment to move product | $257,040 | $105,000 | - | - | - | $257,040 | |
TOTAL RECOMMENDED | $349,857 | $128,740 |
$2,156
90,270
kWh
|
$82,245
-
MMBtu
|
$8,416
-
lb
|
$257,040 | ||
TOTAL IMPLEMENTED | $87,417 | $21,700 |
$2,156
90,270
kWh
|
$81,551
-
MMBtu
|
$3,710
-
lb
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs