Assessment Year | 1999 |
---|---|
Principal Product | Bent and flat fabricated glass |
NAICS |
n/a
|
SIC | 3231: Glass Products, Made of Purchased Glass |
Sales Range | $10 M to 50M |
# of Employees | 145 |
Plant Area |
110,000
ft2
|
Annual Production | 2,000
thousand feet
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $157,475 | 3,679,660 |
kWh
|
$0.043 |
Electricity Demand | $140,295 | 14,901 |
kW-mo/yr
|
$9.42 |
Electricity Fees | $(-7,140.0) | - |
|
- |
Natural Gas | $115,191 | 22,872 |
MMBtu
|
$5.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $162,022 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $102,451 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $3,196 | $12,350 | - | - | $3,196 | - | - | - | - | |
02 | 2.2442: Preheat combustion air with waste heat | $6,652 | $4,300 | - | - | - |
$6,652
-
MMBtu
|
- | - | - | |
03 | 2.7241: Install outside air damper / economizer on hvac unit | $600 | $1,290 | - | - | - |
$600
-
MMBtu
|
- | - | - | |
04 | 2.2511: Insulate bare equipment | $24,192 | $5,439 | - | - | - |
$24,192
-
MMBtu
|
- | - | - | |
05 | 2.7122: Disconnect ballasts | $203 | $80 |
$203
4,982
kWh
|
- | - | - | - | - | - | |
06 | 2.6218: Turn off equipment when not in use | $36 | - |
$36
879
kWh
|
- | - | - | - | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $730 | $198 |
$730
17,878
kWh
|
- | - | - | - | - | - | |
08 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $54,120 | - | - |
$54,120
-
kW-mo/yr
|
- | - | - | - | - | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $168 | $25 |
$168
4,103
kWh
|
- | - | - | - | - | - | |
10 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $7,120 | $1,260 | - | - | - | - | - |
$7,120
-
lb
|
- | |
11 | 3.4111: Use closed cycle process to minimize waste water production | $40,226 | $12,000 | - | - | - | - |
$40,226
-
gal
|
- | - | |
12 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $3,840 | $1,260 | - | - | - | - | - |
$3,840
-
lb
|
- | |
13 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $7,999 | $11,000 | - | - | - | - | - |
$7,999
-
lb
|
- | |
14 | 3.5311: Recover and reuse waste material | $6,940 | $1,800 | - | - | - | - | - |
$6,940
-
lb
|
- | |
15 | 4.511: Expand operations into unused space | $6,000 | $1,050 | - | - | - | - | - | - | $6,000 | |
TOTAL RECOMMENDED | $162,022 | $52,052 |
$1,137
27,842
kWh
|
$54,120
-
kW-mo/yr
|
$3,196 |
$31,444
-
MMBtu
|
$40,226
-
gal
|
$25,899
-
lb
|
$6,000 | ||
TOTAL IMPLEMENTED | $102,451 | $10,889 |
$239
5,861
kWh
|
$54,120
-
kW-mo/yr
|
- |
$24,192
-
MMBtu
|
- |
$17,900
-
lb
|
$6,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs