Assessment Year | 1999 |
---|---|
Principal Product | Automotive parts |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 468 |
Plant Area |
144,000
ft2
|
Annual Production | 2,860,000
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $47,290 | 3,683,470 |
kWh
|
$0.013 |
Electricity Demand | $107,109 | 9,572 |
kW-mo/yr
|
$11.19 |
Electricity Fees | $57,854 | - |
|
- |
Natural Gas | $59,910 | 13,650 |
MMBtu
|
$4.39 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $120,403 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $107,926 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | LPG Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $199 | $250 |
$199
6,741
kWh
|
- | - | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $619 | $160 |
$619
21,688
kWh
|
- | - | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,368 | $15 |
$1,368
48,066
kWh
|
- | - | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,060 | $15 |
$1,060
36,928
kWh
|
- | - | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $486 | $100 |
$486
16,999
kWh
|
- | - | - | - | - | |
06 | 2.2437: Recover waste heat from equipment | $2,728 | $740 | - | - |
$2,728
-
MMBtu
|
- | - | - | |
07 | 2.2442: Preheat combustion air with waste heat | $5,666 | $4,400 | - | - |
$5,666
-
MMBtu
|
- | - | - | |
08 | 2.1331: Burn a less expensive grade of fuel | $730 | $1,826 | - |
$(-2,839.0)
-
MMBtu
|
$3,569
-
MMBtu
|
- | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $610 | $608 |
$610
4,103
kWh
|
- | - | - | - | - | |
10 | 2.1331: Burn a less expensive grade of fuel | $1,824 | $11,000 | - |
$(-12,763.0)
-
MMBtu
|
$14,587
-
MMBtu
|
- | - | - | |
11 | 3.5316: Contract a wood pallet recycling company | $720 | $200 | - | - | - |
$720
-
lb
|
- | - | |
12 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $393 | - | - | - | - | - |
$393
-
lb
|
- | |
13 | 4.431: Train operators for maximum operating efficiency | $104,000 | $32,500 | - | - | - | - | - | $104,000 | |
TOTAL RECOMMENDED | $120,403 | $51,814 |
$4,342
134,525
kWh
|
$(-15,602.0)
-
MMBtu
|
$26,550
-
MMBtu
|
$720
-
lb
|
$393
-
lb
|
$104,000 | ||
TOTAL IMPLEMENTED | $107,926 | $32,790 |
$3,533
123,681
kWh
|
- | - | - |
$393
-
lb
|
$104,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | LPG Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs