ITAC Assessment: WV0161
ITAC logo
ITAC Assessment: WV0161
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Automotive parts
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $50
M
to 100
M
# of Employees 468
Plant Area 144,000
ft2
Annual Production 2,860,000
pieces
Production Hrs. Annual 4,420
hrs
Location (State) Maryland

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $47,290 3,683,470
kWh
Electricity Demand $107,109 9,572
kW-mo/yr
Electricity Fees $57,854 -
Natural Gas $59,910 13,650
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $120,403 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $107,926

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings LPG Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $199 $250 $199
6,741
kWh
- - - - -
02 2.4221: Install compressor air intakes in coolest locations $619 $160 $619
21,688
kWh
- - - - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,368 $15 $1,368
48,066
kWh
- - - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $1,060 $15 $1,060
36,928
kWh
- - - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $486 $100 $486
16,999
kWh
- - - - -
06 2.2437: Recover waste heat from equipment $2,728 $740 - - $2,728
-
MMBtu
- - -
07 2.2442: Preheat combustion air with waste heat $5,666 $4,400 - - $5,666
-
MMBtu
- - -
08 2.1331: Burn a less expensive grade of fuel $730 $1,826 - $(-2,839.0)
-
MMBtu
$3,569
-
MMBtu
- - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $610 $608 $610
4,103
kWh
- - - - -
10 2.1331: Burn a less expensive grade of fuel $1,824 $11,000 - $(-12,763.0)
-
MMBtu
$14,587
-
MMBtu
- - -
11 3.5316: Contract a wood pallet recycling company $720 $200 - - - $720
-
lb
- -
12 3.5212: Regrind, reuse, or sell scrap plastic parts $393 - - - - - $393
-
lb
-
13 4.431: Train operators for maximum operating efficiency $104,000 $32,500 - - - - - $104,000
TOTAL RECOMMENDED $120,403 $51,814 $4,342
134,525
kWh
$(-15,602.0)
-
MMBtu
$26,550
-
MMBtu
$720
-
lb
$393
-
lb
$104,000
TOTAL IMPLEMENTED $107,926 $32,790 $3,533
123,681
kWh
- - - $393
-
lb
$104,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings LPG Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs