Assessment Year | 1999 |
---|---|
Principal Product | Carburetors, CV Joints |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 325 |
Plant Area |
209,000
ft2
|
Annual Production | 300,000
pieces
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $146,871 | 2,578,839 |
kWh
|
$0.057 |
Electricity Demand | $46,775 | 8,612 |
kW-mo/yr
|
$5.43 |
Electricity Fees | $1,887 | - |
|
- |
Natural Gas | $41,905 | 5,861 |
MMBtu
|
$7.15 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $196,765 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $29,382 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4314: Use synthetic lubricant | $2,790 | $970 |
$2,790
71,805
kWh
|
- | - | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $979 | $46 |
$979
25,205
kWh
|
- | - | - | - | - | |
03 | 2.7241: Install outside air damper / economizer on hvac unit | $1,445 | $2,052 |
$1,445
37,222
kWh
|
- | - | - | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,203 | $520 |
$2,203
56,858
kWh
|
- | - | - | - | - | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $1,009 | $977 |
$1,009
7,620
kWh
|
- | - | - | - | - | |
06 | 2.2511: Insulate bare equipment | $623 | $450 | - | - | - |
$623
-
MMBtu
|
- | - | |
07 | 2.2414: Use waste heat from hot flue gases to preheat | $6,485 | $7,500 | - | - | - |
$6,485
-
MMBtu
|
- | - | |
08 | 2.2444: Use hot process fluids to preheat incoming process fluids | $1,488 | $1,650 | - | - | - |
$1,488
-
MMBtu
|
- | - | |
09 | 2.1113: Reduce combustion air flow to optimum | $3,445 | $1,000 | - | - | - |
$3,445
-
MMBtu
|
- | - | |
10 | 2.3212: Optimize plant power factor | $1,059 | $1,879 | - | - | $1,059 | - | - | - | |
11 | 2.7124: Make a practice of turning off lights when not needed | $3,812 | $224 |
$3,812
98,183
kWh
|
- | - | - | - | - | |
12 | 2.8123: Pay utility bills on time | $328 | - | - | - | - | - | - | $328 | |
13 | 3.3131: Use evaporation to concentrate material | $7,217 | $4,265 | - | - | - | - |
$7,217
-
Tgal
|
- | |
14 | 4.422: Utilize outside contracting | $14,816 | - | - | - | - | - | - | $14,816 | |
15 | 4.652: Replace existing equipment with more suitable substitutes | $146,629 | $250,000 | - | - | - | - | - | $146,629 | |
16 | 4.632: Change operating conditions | $2,437 | - | - |
$2,437
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $196,765 | $271,533 |
$12,238
296,893
kWh
|
$2,437
-
kW-mo/yr
|
$1,059 |
$12,041
-
MMBtu
|
$7,217
-
Tgal
|
$161,773 | ||
TOTAL IMPLEMENTED | $29,382 | $3,737 |
$10,793
259,671
kWh
|
- | - |
$3,445
-
MMBtu
|
- | $15,144 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs