Assessment Year | 1999 |
---|---|
Principal Product | Boxes(PVC, Fiberglass, Steel) |
NAICS |
n/a
|
SIC | 3613: Switchgear and Switchboard Apparatus |
Sales Range | $10 M to 50M |
# of Employees | 147 |
Plant Area |
300,000
ft2
|
Annual Production | 6,000,000
pieces
|
Production Hrs. Annual | 8,496
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $299,238 | 5,897,421 |
kWh
|
$0.051 |
Electricity Demand | $67,167 | 13,554 |
kW-mo/yr
|
$4.96 |
Electricity Fees | $3,849 | - |
|
- |
Natural Gas | $60,612 | 20,616 |
MMBtu
|
$2.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $117,797 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,378 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $17,572 | $15,591 |
$17,572
446,659
kWh
|
- | - | - | - | - | - | |
02 | 2.1113: Reduce combustion air flow to optimum | $1,158 | $672 | - |
$1,158
-
MMBtu
|
- | - | - | - | - | |
03 | 2.1331: Burn a less expensive grade of fuel | $4,324 | $4,800 | - | - | - | - | - | $4,324 | - | |
04 | 2.7124: Make a practice of turning off lights when not needed | $7,399 | $1,876 |
$7,399
163,834
kWh
|
- | - | - | - | - | - | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $732 | $671 |
$732
5,569
kWh
|
- | - | - | - | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $2,548 | $144 |
$2,548
64,771
kWh
|
- | - | - | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,743 | $60 |
$1,743
44,256
kWh
|
- | - | - | - | - | - | |
08 | 2.7243: Improve air circulation with destratification fans / other methods | $6,888 | $4,000 | - |
$6,888
-
MMBtu
|
- | - | - | - | - | |
09 | 2.1224: Replace boiler | $2,866 | $49,515 | - |
$2,866
-
MMBtu
|
- | - | - | - | - | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,638 | $23 |
$5,638
143,318
kWh
|
- | - | - | - | - | - | |
11 | 3.3131: Use evaporation to concentrate material | $4,852 | $3,756 | - | - |
$4,852
-
Tgal
|
- | - | - | - | |
12 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $560 | - | - | - | - | - |
$560
-
lb
|
- | - | |
13 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $600 | $42 | - | - | - |
$600
-
lb
|
- | - | - | |
14 | 4.423: Move product using mechanical means | $4,667 | $260 | - | - | - | - | - | - | $4,667 | |
15 | 4.521: Clear and rent existing space | $56,250 | $4,800 | - | - | - | - | - | $56,250 | - | |
TOTAL RECOMMENDED | $117,797 | $86,210 |
$35,632
868,407
kWh
|
$10,912
-
MMBtu
|
$4,852
-
Tgal
|
$600
-
lb
|
$560
-
lb
|
$60,574 | $4,667 | ||
TOTAL IMPLEMENTED | $20,378 | $3,488 |
$18,060
421,748
kWh
|
$1,158
-
MMBtu
|
- |
$600
-
lb
|
$560
-
lb
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs