ITAC Assessment: WV0156
ITAC logo
ITAC Assessment: WV0156
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Boxes(PVC, Fiberglass, Steel)
NAICS
n/a
SIC 3613: Switchgear and Switchboard Apparatus
Sales Range $10
M
to 50
M
# of Employees 147
Plant Area 300,000
ft2
Annual Production 6,000,000
pieces
Production Hrs. Annual 8,496
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $299,238 5,897,421
kWh
Electricity Demand $67,167 13,554
kW-mo/yr
Electricity Fees $3,849 -
Natural Gas $60,612 20,616
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $117,797 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,378

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Administrative Changes Savings Primary Product Savings
01 2.2614: Use cooling tower or economizer to replace chiller cooling $17,572 $15,591 $17,572
446,659
kWh
- - - - - -
02 2.1113: Reduce combustion air flow to optimum $1,158 $672 - $1,158
-
MMBtu
- - - - -
03 2.1331: Burn a less expensive grade of fuel $4,324 $4,800 - - - - - $4,324 -
04 2.7124: Make a practice of turning off lights when not needed $7,399 $1,876 $7,399
163,834
kWh
- - - - - -
05 2.7111: Reduce illumination to minimum necessary levels $732 $671 $732
5,569
kWh
- - - - - -
06 2.4221: Install compressor air intakes in coolest locations $2,548 $144 $2,548
64,771
kWh
- - - - - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,743 $60 $1,743
44,256
kWh
- - - - - -
08 2.7243: Improve air circulation with destratification fans / other methods $6,888 $4,000 - $6,888
-
MMBtu
- - - - -
09 2.1224: Replace boiler $2,866 $49,515 - $2,866
-
MMBtu
- - - - -
10 2.4231: Reduce the pressure of compressed air to the minimum required $5,638 $23 $5,638
143,318
kWh
- - - - - -
11 3.3131: Use evaporation to concentrate material $4,852 $3,756 - - $4,852
-
Tgal
- - - -
12 3.5212: Regrind, reuse, or sell scrap plastic parts $560 - - - - - $560
-
lb
- -
13 3.5212: Regrind, reuse, or sell scrap plastic parts $600 $42 - - - $600
-
lb
- - -
14 4.423: Move product using mechanical means $4,667 $260 - - - - - - $4,667
15 4.521: Clear and rent existing space $56,250 $4,800 - - - - - $56,250 -
TOTAL RECOMMENDED $117,797 $86,210 $35,632
868,407
kWh
$10,912
-
MMBtu
$4,852
-
Tgal
$600
-
lb
$560
-
lb
$60,574 $4,667
TOTAL IMPLEMENTED $20,378 $3,488 $18,060
421,748
kWh
$1,158
-
MMBtu
- $600
-
lb
$560
-
lb
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Administrative Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs