| Assessment Year | 1998 |
|---|---|
| Principal Product | Hardwood Caskets |
| NAICS |
n/a
|
| SIC | 3995: Burial Caskets |
| Sales Range | $10 M to 50M |
| # of Employees | 141 |
| Plant Area |
291,600
ft2
|
| Annual Production | 22,100
pieces
|
| Production Hrs. Annual | 5,200
hrs
|
| Location (State) | West Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $224,487 | 4,305,100 |
kWh
|
$0.052 |
| Natural Gas | $17,589 | 1,686 |
MMBtu
|
$10.43 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $154,015 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $31,043 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $2,607 | $1,160 | - |
$2,607
-
MMBtu
|
- | - | - | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $298 | $116 |
$298
5,569
kWh
|
- | - | - | - | |
| 03 | 2.2136: Install / repair insulation on steam lines | $372 | $89 | - |
$372
-
MMBtu
|
- | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $164 | $40 |
$164
2,931
kWh
|
- | - | - | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $1,372 | $1,602 |
$1,372
127,198
kWh
|
- | - | - | - | |
| 06 | 2.1331: Burn a less expensive grade of fuel | $3,468 | $3,600 | - | - | - | $3,468 | - | |
| 07 | 2.7243: Improve air circulation with destratification fans / other methods | $7,036 | $7,700 | - |
$7,036
-
MMBtu
|
- | - | - | |
| 08 | 2.2414: Use waste heat from hot flue gases to preheat | $10,304 | $3,700 | - |
$10,304
-
MMBtu
|
- | - | - | |
| 09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,574 | $360 |
$1,574
30,188
kWh
|
- | - | - | - | |
| 10 | 2.7122: Disconnect ballasts | $620 | $1,024 |
$620
12,016
kWh
|
- | - | - | - | |
| 11 | 2.8123: Pay utility bills on time | $4,142 | - | - | - | - | $4,142 | - | |
| 12 | 2.8113: Purchase gas directly from a contract gas supplier | $10,419 | - | - | - | - | $10,419 | - | |
| 13 | 2.7124: Make a practice of turning off lights when not needed | $10,895 | $880 |
$10,895
208,968
kWh
|
- | - | - | - | |
| 14 | 3.5217: Reuse / recycle/ sell paper products | $1,600 | $288 | - | - |
$1,600
-
lb
|
- | - | |
| 15 | 3.5311: Recover and reuse waste material | $5,807 | $301 | - | - |
$5,807
-
lb
|
- | - | |
| 16 | 4.131: Modify process to reduce material use/cost | $93,337 | $16,128 | - | - | - | - | $93,337 | |
| TOTAL RECOMMENDED | $154,015 | $36,988 |
$14,923
386,870
kWh
|
$20,319
-
MMBtu
|
$7,407
-
lb
|
$18,029 | $93,337 | ||
| TOTAL IMPLEMENTED | $31,043 | $7,983 |
$14,625
381,301
kWh
|
$10,676
-
MMBtu
|
$1,600
-
lb
|
$4,142 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs