ITAC Assessment: WV0153
ITAC logo
ITAC Assessment: WV0153
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Hardwood Caskets
NAICS
n/a
SIC 3995: Burial Caskets
Sales Range $10
M
to 50
M
# of Employees 141
Plant Area 291,600
ft2
Annual Production 22,100
pieces
Production Hrs. Annual 5,200
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $224,487 4,305,100
kWh
Natural Gas $17,589 1,686
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $154,015 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $31,043

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.2511: Insulate bare equipment $2,607 $1,160 - $2,607
-
MMBtu
- - -
02 2.4221: Install compressor air intakes in coolest locations $298 $116 $298
5,569
kWh
- - - -
03 2.2136: Install / repair insulation on steam lines $372 $89 - $372
-
MMBtu
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $164 $40 $164
2,931
kWh
- - - -
05 2.4133: Use most efficient type of electric motors $1,372 $1,602 $1,372
127,198
kWh
- - - -
06 2.1331: Burn a less expensive grade of fuel $3,468 $3,600 - - - $3,468 -
07 2.7243: Improve air circulation with destratification fans / other methods $7,036 $7,700 - $7,036
-
MMBtu
- - -
08 2.2414: Use waste heat from hot flue gases to preheat $10,304 $3,700 - $10,304
-
MMBtu
- - -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,574 $360 $1,574
30,188
kWh
- - - -
10 2.7122: Disconnect ballasts $620 $1,024 $620
12,016
kWh
- - - -
11 2.8123: Pay utility bills on time $4,142 - - - - $4,142 -
12 2.8113: Purchase gas directly from a contract gas supplier $10,419 - - - - $10,419 -
13 2.7124: Make a practice of turning off lights when not needed $10,895 $880 $10,895
208,968
kWh
- - - -
14 3.5217: Reuse / recycle/ sell paper products $1,600 $288 - - $1,600
-
lb
- -
15 3.5311: Recover and reuse waste material $5,807 $301 - - $5,807
-
lb
- -
16 4.131: Modify process to reduce material use/cost $93,337 $16,128 - - - - $93,337
TOTAL RECOMMENDED $154,015 $36,988 $14,923
386,870
kWh
$20,319
-
MMBtu
$7,407
-
lb
$18,029 $93,337
TOTAL IMPLEMENTED $31,043 $7,983 $14,625
381,301
kWh
$10,676
-
MMBtu
$1,600
-
lb
$4,142 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs