Assessment Year | 1998 |
---|---|
Principal Product | Building Wire and Cable, Industrial Power Cable |
NAICS |
n/a
|
SIC | 3357: Drawing and Insulating of Nonferrous Wire |
Sales Range | $50 M to 100M |
# of Employees | 296 |
Plant Area |
500,000
ft2
|
Annual Production | 60,000,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $506,162 | 17,451,055 |
kWh
|
$0.029 |
Electricity Demand | $42,984 | 38,039 |
kW-mo/yr
|
$1.13 |
Electricity Fees | $55,743 | - |
|
- |
Natural Gas | $150,418 | 45,213 |
MMBtu
|
$3.33 |
LPG | $16,686 | 2,411 |
MMBtu
|
$6.92 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $112,241 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $50,064 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | LPG Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,885 | $881 |
$3,828
152,989
kWh
|
- | $57 | - | - | - | - | - | - | - | |
02 | 2.2437: Recover waste heat from equipment | $12,972 | $5,703 | - | - | - |
$12,972
-
MMBtu
|
- | - | - | - | - | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,002 | $5,805 |
$1,972
78,839
kWh
|
- | $30 | - | - | - | - | - | - | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $6,888 | $6,000 | - | - | - |
$6,888
-
MMBtu
|
- | - | - | - | - | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $9,417 | $1,000 | - | - | - |
$9,417
-
MMBtu
|
- | - | - | - | - | - | |
06 | 2.7111: Reduce illumination to minimum necessary levels | $6,664 | $270 |
$6,182
247,362
kWh
|
$384
-
kW-mo/yr
|
$98 | - | - | - | - | - | - | - | |
07 | 2.4239: Eliminate or reduce compressed air usage | $3,987 | $1,424 |
$3,928
157,093
kWh
|
- | $59 | - | - | - | - | - | - | - | |
08 | 2.1332: Convert combustion equipment to burn natural gas | $15,436 | $142,800 | - | - | - |
$(-8,149.0)
-
MMBtu
|
$16,686
-
MMBtu
|
- | - | $6,899 | - | - | |
09 | 2.1212: Operate boilers on high fire setting | $37,680 | - | - | - | - |
$37,680
-
MMBtu
|
- | - | - | - | - | - | |
10 | 3.1191: Change procedures / equipment / operating conditions | $171 | $82 | - | - | - | - | - | - | - | - | - | $171 | |
11 | 3.5316: Contract a wood pallet recycling company | $5,658 | - | - | - | - | - | - | - |
$5,658
-
lb
|
- | - | - | |
12 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $(-400.0) | - | - | - | - | - | - | - |
$600
-
lb
|
- | $(-1,000.0) | - | |
13 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $7,881 | $17,414 | - | - | - | - | - |
$7,881
-
gal
|
- | - | - | - | |
TOTAL RECOMMENDED | $112,241 | $181,379 |
$15,910
636,283
kWh
|
$384
-
kW-mo/yr
|
$244 |
$58,808
-
MMBtu
|
$16,686
-
MMBtu
|
$7,881
-
gal
|
$6,258
-
lb
|
$6,899 | $(-1,000.0) | $171 | ||
TOTAL IMPLEMENTED | $50,064 | $26,692 |
$13,938
557,444
kWh
|
$384
-
kW-mo/yr
|
$214 |
$22,389
-
MMBtu
|
- |
$7,881
-
gal
|
$6,258
-
lb
|
- | $(-1,000.0) | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | LPG Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs