ITAC Assessment: WV0149
ITAC logo
ITAC Assessment: WV0149
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Automotive Gaskets
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 100,000
ft2
Annual Production 10,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $134,022 5,028,722
kWh
Electricity Demand $119,461 12,768
kW-mo/yr
Electricity Fees $18,075 -
Natural Gas $215,323 46,066
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $162,417 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $87,523

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Other Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.4221: Install compressor air intakes in coolest locations $886 $98 $886
29,308
kWh
- - - - - - -
02 2.6218: Turn off equipment when not in use $5,271 - $5,271
174,385
kWh
- - - - - - -
03 2.6213: Turn off steam / hot water lines leading to space heating units $16,316 - - - $16,316
-
MMBtu
- - - - -
04 2.8113: Purchase gas directly from a contract gas supplier $53,897 - - - $53,897
-
MMBtu
- - - - -
05 2.1331: Burn a less expensive grade of fuel $4,200 $7,200 - - - $300
-
MMBtu
- - $3,900 -
06 2.2414: Use waste heat from hot flue gases to preheat $6,988 $3,005 - - $6,988
-
MMBtu
- - - - -
07 2.8123: Pay utility bills on time $1,820 - - - - - - - - $1,820
08 2.2511: Insulate bare equipment $1,667 $1,120 - - $1,667
-
MMBtu
- - - - -
09 2.2511: Insulate bare equipment $411 $320 - - $411
-
MMBtu
- - - - -
10 2.2514: Cover open tanks $1,515 $4,656 - - $1,515
-
MMBtu
- - - - -
11 2.3212: Optimize plant power factor $4,342 $14,610 - $4,342 - - - - - -
12 2.4133: Use most efficient type of electric motors $118 $5,030 $118
38,980
kWh
- - - - - - -
13 2.2136: Install / repair insulation on steam lines $2,715 $3,272 - - $2,715
-
MMBtu
- - - - -
14 2.1113: Reduce combustion air flow to optimum $2,046 $1,000 - - $2,046
-
MMBtu
- - - - -
15 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,365 $960 $1,365
45,135
kWh
- - - - - - -
16 3.5316: Contract a wood pallet recycling company $3,840 $42 - - - - - $3,840
-
lb
- -
17 3.3131: Use evaporation to concentrate material $1,020 $1,068 - - - - $1,020
-
Tgal
- - -
18 4.431: Train operators for maximum operating efficiency $54,000 - - - - - - - $54,000 -
TOTAL RECOMMENDED $162,417 $42,381 $7,640
287,808
kWh
$4,342 $85,555
-
MMBtu
$300
-
MMBtu
$1,020
-
Tgal
$3,840
-
lb
$57,900 $1,820
TOTAL IMPLEMENTED $87,523 $10,744 $6,754
258,500
kWh
- $21,109
-
MMBtu
- - $3,840
-
lb
$54,000 $1,820
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Other Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs