ITAC Assessment: OR0451
ITAC logo
ITAC Assessment: OR0451
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Precast Concrete
NAICS 327390: Other Concrete Product Manufacturing
SIC 3272: Concrete Products, Except Block and Brick
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area
n/a
Annual Production 19,334
units
Production Hrs. Annual 2,080
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $48,063 1,424,000
kWh
Electricity Demand $28,323 5,988
kW-mo/yr
Electricity Fees $3,967 -
Natural Gas $87,834 15,118
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $31,661 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,316

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 4.513: Re-arrange equipment layout to reduce labor costs $20,100 $3,525 - - - $20,100
02 2.4224: Upgrade controls on compressors $5,370 $19,500 $5,370
159,000
kWh
- - -
03 2.7124: Make a practice of turning off lights when not needed $3,488 - $2,778
82,380
kWh
- - $710
04 2.4133: Use most efficient type of electric motors $1,828 $360 $897
26,600
kWh
$931
-
kW-mo/yr
- -
05 2.1231: Establish burner maintenance schedule for boilers $875 $300 - - $875
-
MMBtu
-
TOTAL RECOMMENDED $31,661 $23,685 $9,045
267,980
kWh
$931
-
kW-mo/yr
$875
-
MMBtu
$20,810
TOTAL IMPLEMENTED $5,316 $360 $3,675
108,980
kWh
$931
-
kW-mo/yr
- $710
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs