| Assessment Year | 2004 |
|---|---|
| Principal Product | Precast Concrete |
| NAICS | 327390: Other Concrete Product Manufacturing |
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $10 M to 50M |
| # of Employees | 90 |
| Plant Area |
n/a
|
| Annual Production | 19,334
units
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $48,063 | 1,424,000 |
kWh
|
$0.034 |
| Electricity Demand | $28,323 | 5,988 |
kW-mo/yr
|
$4.73 |
| Electricity Fees | $3,967 | - |
|
- |
| Natural Gas | $87,834 | 15,118 |
MMBtu
|
$5.81 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $31,661 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,316 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 4.513: Re-arrange equipment layout to reduce labor costs | $20,100 | $3,525 | - | - | - | $20,100 | |
| 02 | 2.4224: Upgrade controls on compressors | $5,370 | $19,500 |
$5,370
159,000
kWh
|
- | - | - | |
| 03 | 2.7124: Make a practice of turning off lights when not needed | $3,488 | - |
$2,778
82,380
kWh
|
- | - | $710 | |
| 04 | 2.4133: Use most efficient type of electric motors | $1,828 | $360 |
$897
26,600
kWh
|
$931
-
kW-mo/yr
|
- | - | |
| 05 | 2.1231: Establish burner maintenance schedule for boilers | $875 | $300 | - | - |
$875
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $31,661 | $23,685 |
$9,045
267,980
kWh
|
$931
-
kW-mo/yr
|
$875
-
MMBtu
|
$20,810 | ||
| TOTAL IMPLEMENTED | $5,316 | $360 |
$3,675
108,980
kWh
|
$931
-
kW-mo/yr
|
- | $710 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs