Assessment Year | 1998 |
---|---|
Principal Product | Convex tempered &etched glass |
NAICS |
n/a
|
SIC | 3231: Glass Products, Made of Purchased Glass |
Sales Range | $5 M to 10M |
# of Employees | 55 |
Plant Area |
89,462
ft2
|
Annual Production | 1,000
thousand feet
|
Production Hrs. Annual | 1,880
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $60,448 | 1,037,515 |
kWh
|
$0.058 |
Natural Gas | $119,977 | 35,279 |
MMBtu
|
$3.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $89,809 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,937 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7314: Reduce ventilation air | $314 | $350 | - |
$314
-
MMBtu
|
- | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $38 | $136 |
$38
586
kWh
|
- | - | - | - | |
03 | 2.1113: Reduce combustion air flow to optimum | $2,135 | $1,000 | - |
$2,135
-
MMBtu
|
- | - | - | |
04 | 2.2136: Install / repair insulation on steam lines | $408 | $3,072 | - |
$408
-
MMBtu
|
- | - | - | |
05 | 2.4314: Use synthetic lubricant | $87 | $217 |
$87
1,465
kWh
|
- | - | - | - | |
06 | 2.2511: Insulate bare equipment | $506 | $263 | - |
$506
-
MMBtu
|
- | - | - | |
07 | 2.2437: Recover waste heat from equipment | $18,084 | $2,893 | - |
$18,084
-
MMBtu
|
- | - | - | |
08 | 2.2514: Cover open tanks | $4,417 | $699 | - |
$4,417
-
MMBtu
|
- | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $136 | $1,439 |
$136
2,345
kWh
|
- | - | - | - | |
10 | 2.8123: Pay utility bills on time | $657 | - | - | - | - | - | $657 | |
11 | 3.3122: Use filtration, centrifuging to remove contaminants | $783 | $850 | - | - |
$783
-
Tgal
|
- | - | |
12 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $5,004 | $11,000 | - | - | - |
$5,004
-
lb
|
- | |
13 | 4.521: Clear and rent existing space | $57,240 | $16,800 | - | - | - | - | $57,240 | |
TOTAL RECOMMENDED | $89,809 | $38,719 |
$261
4,396
kWh
|
$25,864
-
MMBtu
|
$783
-
Tgal
|
$5,004
-
lb
|
$57,897 | ||
TOTAL IMPLEMENTED | $8,937 | $7,627 |
$223
3,810
kWh
|
$7,274
-
MMBtu
|
$783
-
Tgal
|
- | $657 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs