ITAC Assessment: WV0146
ITAC logo
ITAC Assessment: WV0146
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Convex tempered &etched glass
NAICS
n/a
SIC 3231: Glass Products, Made of Purchased Glass
Sales Range $5
M
to 10
M
# of Employees 55
Plant Area 89,462
ft2
Annual Production 1,000
thousand feet
Production Hrs. Annual 1,880
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $60,448 1,037,515
kWh
Natural Gas $119,977 35,279
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $89,809 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,937

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.7314: Reduce ventilation air $314 $350 - $314
-
MMBtu
- - -
02 2.4221: Install compressor air intakes in coolest locations $38 $136 $38
586
kWh
- - - -
03 2.1113: Reduce combustion air flow to optimum $2,135 $1,000 - $2,135
-
MMBtu
- - -
04 2.2136: Install / repair insulation on steam lines $408 $3,072 - $408
-
MMBtu
- - -
05 2.4314: Use synthetic lubricant $87 $217 $87
1,465
kWh
- - - -
06 2.2511: Insulate bare equipment $506 $263 - $506
-
MMBtu
- - -
07 2.2437: Recover waste heat from equipment $18,084 $2,893 - $18,084
-
MMBtu
- - -
08 2.2514: Cover open tanks $4,417 $699 - $4,417
-
MMBtu
- - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $136 $1,439 $136
2,345
kWh
- - - -
10 2.8123: Pay utility bills on time $657 - - - - - $657
11 3.3122: Use filtration, centrifuging to remove contaminants $783 $850 - - $783
-
Tgal
- -
12 3.6193: Install equipment (eg compactor) to reduce disposal costs $5,004 $11,000 - - - $5,004
-
lb
-
13 4.521: Clear and rent existing space $57,240 $16,800 - - - - $57,240
TOTAL RECOMMENDED $89,809 $38,719 $261
4,396
kWh
$25,864
-
MMBtu
$783
-
Tgal
$5,004
-
lb
$57,897
TOTAL IMPLEMENTED $8,937 $7,627 $223
3,810
kWh
$7,274
-
MMBtu
$783
-
Tgal
- $657
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs