Assessment Year | 1997 |
---|---|
Principal Product | Convertible Sofas, Sinuous Springs, and Drop-in Coil Springs |
NAICS |
n/a
|
SIC | 3495: Wire Springs |
Sales Range | $10 M to 50M |
# of Employees | 151 |
Plant Area |
271,702
ft2
|
Annual Production | 55,500,000
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $50,354 | 1,389,508 |
kWh
|
$0.036 |
Electricity Demand | $31,450 | 4,478 |
kW-mo/yr
|
$7.02 |
Electricity Fees | $1,412 | - |
|
- |
Natural Gas | $46,279 | 12,018 |
MMBtu
|
$3.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $67,774 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,366 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $5,870 | $1,500 | - |
$5,870
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7122: Disconnect ballasts | $313 | $150 |
$175
5,569
kWh
|
$138
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4314: Use synthetic lubricant | $1,944 | $275 |
$1,084
35,170
kWh
|
$860
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,232 | $7,102 |
$1,624
39,566
kWh
|
$608
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $1,607 | $561 | - | - |
$1,607
-
MMBtu
|
- | - | - | |
06 | 2.2414: Use waste heat from hot flue gases to preheat | $6,564 | $11,519 | - | - |
$6,564
-
MMBtu
|
- | - | - | |
07 | 3.5316: Contract a wood pallet recycling company | $2,400 | - | - | - | - |
$900
-
lb
|
$1,500 | - | |
08 | 4.652: Replace existing equipment with more suitable substitutes | $46,844 | $20,800 | - | - | - | - | - | $46,844 | |
TOTAL RECOMMENDED | $67,774 | $41,907 |
$2,883
80,305
kWh
|
$7,476
-
kW-mo/yr
|
$8,171
-
MMBtu
|
$900
-
lb
|
$1,500 | $46,844 | ||
TOTAL IMPLEMENTED | $14,366 | $9,588 |
$2,883
80,305
kWh
|
$7,476
-
kW-mo/yr
|
$1,607
-
MMBtu
|
$900
-
lb
|
$1,500 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs