Assessment Year | 1998 |
---|---|
Principal Product | cold rolled stripped carbon |
NAICS |
n/a
|
SIC | 3316: Cold-Rolled Steel Sheet, Strip, and Bars |
Sales Range | $10 M to 50M |
# of Employees | 175 |
Plant Area |
1,089,000
ft2
|
Annual Production | 0
ton
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,267,699 | 16,316,530 |
kWh
|
$0.078 |
Fuel Oil #1 | $864,235 | 198,728 |
MMBtu
|
$4.35 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $148,110 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $102,820 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #1 Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,705 | $2,273 |
$3,705
47,773
kWh
|
- | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $1,917 | $248 |
$1,917
24,619
kWh
|
- | - | - | |
03 | 2.4314: Use synthetic lubricant | $3,504 | $405 |
$3,504
45,135
kWh
|
- | - | - | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $5,802 | $1,000 | - |
$5,802
-
MMBtu
|
- | - | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $5,194 | $2,900 | - |
$5,194
-
MMBtu
|
- | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,834 | $6,000 |
$6,834
87,925
kWh
|
- | - | - | |
07 | 2.7241: Install outside air damper / economizer on hvac unit | $6,854 | $1,210 |
$6,854
88,218
kWh
|
- | - | - | |
08 | 2.4133: Use most efficient type of electric motors | $72,430 | $100,440 |
$72,430
931,125
kWh
|
- | - | - | |
09 | 2.7231: Use radiant heater for spot heating | $18,727 | $350 | - | - | - | $18,727 | |
10 | 3.4111: Use closed cycle process to minimize waste water production | $1,372 | $7,000 | - | - |
$1,372
-
Tgal
|
- | |
11 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $6,796 | $11,000 | - | - | - | $6,796 | |
12 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $3,600 | - | - | - | - | $3,600 | |
13 | 4.511: Expand operations into unused space | $11,375 | $2,520 | - | - | - | $11,375 | |
TOTAL RECOMMENDED | $148,110 | $135,346 |
$95,244
1,224,795
kWh
|
$10,996
-
MMBtu
|
$1,372
-
Tgal
|
$40,498 | ||
TOTAL IMPLEMENTED | $102,820 | $118,638 |
$86,473
1,111,958
kWh
|
- |
$1,372
-
Tgal
|
$14,975 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #1 Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs