Assessment Year | 1997 |
---|---|
Principal Product | Confectioneries |
NAICS |
n/a
|
SIC | 2064: Candy and Other Confectionery Products |
Sales Range | $1 M to 5M |
# of Employees | 35 |
Plant Area |
30,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 5,880
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $32,382 | 805,979 |
kWh
|
$0.040 |
Electricity Demand | $41,830 | 2,325 |
kW-mo/yr
|
$17.99 |
Electricity Fees | $(-3,339.0) | - |
|
- |
Natural Gas | $7,672 | 1,366 |
MMBtu
|
$5.62 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $61,588 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $48,817 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,013 | $235 |
$506
14,068
kWh
|
$507
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $184 | $249 |
$46
1,172
kWh
|
$138
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $391 | $680 |
$391
10,844
kWh
|
- | - | - | - | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $107 | $110 |
$107
2,931
kWh
|
- | - | - | - | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $107 | $80 |
$107
2,931
kWh
|
- | - | - | - | - | - | |
06 | 2.7241: Install outside air damper / economizer on hvac unit | $7,634 | $5,160 |
$7,634
211,899
kWh
|
- | - | - | - | - | - | |
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $90 | $400 | - | - |
$90
-
MMBtu
|
- | - | - | - | |
08 | 2.1123: Install automatic stack damper | $1,234 | $250 | - | - |
$1,234
-
MMBtu
|
- | - | - | - | |
09 | 2.2136: Install / repair insulation on steam lines | $82 | $33 | - | - |
$82
-
MMBtu
|
- | - | - | - | |
10 | 2.2437: Recover waste heat from equipment | $507 | $225 | - | - |
$507
-
MMBtu
|
- | - | - | - | |
11 | 3.4111: Use closed cycle process to minimize waste water production | $1,512 | $2,300 | - | - | - |
$1,512
-
Tgal
|
- | - | - | |
12 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $1,687 | $11,000 |
$(-26.0)
(-879)
kWh
|
- | - | - | $(-367.0) | $2,080 | - | |
13 | 4.432: Cross-train personnel to avoid lost time | $47,040 | - | - | - | - | - | - | - | $47,040 | |
TOTAL RECOMMENDED | $61,588 | $20,722 |
$8,765
242,966
kWh
|
$645
-
kW-mo/yr
|
$1,913
-
MMBtu
|
$1,512
-
Tgal
|
$(-367.0) | $2,080 | $47,040 | ||
TOTAL IMPLEMENTED | $48,817 | $1,277 |
$1,050
29,015
kWh
|
$645
-
kW-mo/yr
|
$82
-
MMBtu
|
- | - | - | $47,040 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs