ITAC Assessment: WV0129
ITAC logo
ITAC Assessment: WV0129
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Plastic Compounding Materials
NAICS
n/a
SIC 3087: Custom Compounding of Purchased Plastics Resins
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 89,400
ft2
Annual Production 30,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $558,308 7,817,116
kWh
Electricity Fees $72,772 -
Natural Gas $47,631 20,356
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $496,263 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,471

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings Increase in Production Savings
01 2.4133: Use most efficient type of electric motors $4,294 $12,594 $4,294
53,048
kWh
- - - -
02 2.4221: Install compressor air intakes in coolest locations $1,704 $205 $1,704
21,102
kWh
- - - -
03 2.4314: Use synthetic lubricant $1,750 $375 $1,750
21,688
kWh
- - - -
04 2.1233: Analyze flue gas for proper air/fuel ratio $550 $500 - $550
-
MMBtu
- - -
05 2.1123: Install automatic stack damper $1,848 $250 - $1,848
-
MMBtu
- - -
06 2.1213: Direct warmest air to combustion intake $240 $1,475 - $240
-
MMBtu
- - -
07 2.2136: Install / repair insulation on steam lines $53 $44 - $53
-
MMBtu
- - -
08 3.5316: Contract a wood pallet recycling company $60,000 $200 - - - $60,000 -
09 3.4115: Recover and reuse cooling water $5,824 $2,300 - - $5,824
-
Tgal
- -
10 4.112: Replace old machine with new automatic multi-station tool $420,000 $35,000 - - - - $420,000
TOTAL RECOMMENDED $496,263 $52,943 $7,748
95,838
kWh
$2,691
-
MMBtu
$5,824
-
Tgal
$60,000 $420,000
TOTAL IMPLEMENTED $12,471 $15,813 $6,044
74,736
kWh
$603
-
MMBtu
$5,824
-
Tgal
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs