ITAC Assessment: IA0244
ITAC logo
ITAC Assessment: IA0244
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Fuel Injection Nozzles
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $10
M
to 50
M
# of Employees 126
Plant Area 150,000
ft2
Annual Production 416,250
pieces
Production Hrs. Annual 7,200
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $73,619 2,271,981
kWh
Electricity Demand $16,135 4,788
kW-mo/yr
Natural Gas $2,094 424
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,260 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,187

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Other Liquid (non-haz) Savings Ancillary Material Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $500 $58 $315
14,361
kWh
$185
-
kW-mo/yr
- - -
02 2.4221: Install compressor air intakes in coolest locations $478 $164 $307
13,775
kWh
$171
-
kW-mo/yr
- - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $128 $137 $79
3,517
kWh
$49
-
kW-mo/yr
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,657 - $1,042
47,186
kWh
$615
-
kW-mo/yr
- - -
05 3.8142: Distill contaminated solvents for reuse $7,765 $16,000 $(-32.0)
(-1,465)
kWh
$(-68.0)
-
kW-mo/yr
- $7,865
-
gal
-
06 3.4151: Minimize water usage $4,559 $9,800 - - $4,559
-
Tgal
- -
07 3.4151: Minimize water usage $173 $72 - - - - $173
TOTAL RECOMMENDED $15,260 $26,231 $1,711
77,374
kWh
$952
-
kW-mo/yr
$4,559
-
Tgal
$7,865
-
gal
$173
TOTAL IMPLEMENTED $5,187 $9,995 $394
17,878
kWh
$234
-
kW-mo/yr
$4,559
-
Tgal
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Other Liquid (non-haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs