ITAC Assessment: WV0128
ITAC logo
ITAC Assessment: WV0128
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Jumper and Fuel Lines for Automobiles
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $10
M
to 50
M
# of Employees 301
Plant Area 165,000
ft2
Annual Production 5,400,000
pieces
Production Hrs. Annual 6,120
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $272,859 5,379,836
kWh
Natural Gas $98,491 24,464
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $224,702 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Primary Product Savings
01 2.4221: Install compressor air intakes in coolest locations $892 $150 $892
17,585
kWh
- - -
02 2.2625: Chill water to the highest temperature possible $3,725 $550 $3,725
73,271
kWh
- - -
03 2.1213: Direct warmest air to combustion intake $2,800 $4,700 - $2,800
-
MMBtu
- -
04 2.2511: Insulate bare equipment $9,736 $713 - $9,736
-
MMBtu
- -
05 2.2511: Insulate bare equipment $109 $33 - $109
-
MMBtu
- -
06 3.4111: Use closed cycle process to minimize waste water production $2,400 $6,300 - - $2,400
-
Tgal
-
07 3.4115: Recover and reuse cooling water $2,540 $9,300 - - $2,540
-
Tgal
-
08 4.122: Develop standard procedures to improve internal yields $202,500 $250,000 - - - $202,500
TOTAL RECOMMENDED $224,702 $271,746 $4,617
90,856
kWh
$12,645
-
MMBtu
$4,940
-
Tgal
$202,500
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs