Assessment Year | 1997 |
---|---|
Principal Product | Jumper and Fuel Lines for Automobiles |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 301 |
Plant Area |
165,000
ft2
|
Annual Production | 5,400,000
pieces
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $272,859 | 5,379,836 |
kWh
|
$0.051 |
Natural Gas | $98,491 | 24,464 |
MMBtu
|
$4.03 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $224,702 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $892 | $150 |
$892
17,585
kWh
|
- | - | - | |
02 | 2.2625: Chill water to the highest temperature possible | $3,725 | $550 |
$3,725
73,271
kWh
|
- | - | - | |
03 | 2.1213: Direct warmest air to combustion intake | $2,800 | $4,700 | - |
$2,800
-
MMBtu
|
- | - | |
04 | 2.2511: Insulate bare equipment | $9,736 | $713 | - |
$9,736
-
MMBtu
|
- | - | |
05 | 2.2511: Insulate bare equipment | $109 | $33 | - |
$109
-
MMBtu
|
- | - | |
06 | 3.4111: Use closed cycle process to minimize waste water production | $2,400 | $6,300 | - | - |
$2,400
-
Tgal
|
- | |
07 | 3.4115: Recover and reuse cooling water | $2,540 | $9,300 | - | - |
$2,540
-
Tgal
|
- | |
08 | 4.122: Develop standard procedures to improve internal yields | $202,500 | $250,000 | - | - | - | $202,500 | |
TOTAL RECOMMENDED | $224,702 | $271,746 |
$4,617
90,856
kWh
|
$12,645
-
MMBtu
|
$4,940
-
Tgal
|
$202,500 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs