ITAC Assessment: WV0125
ITAC logo
ITAC Assessment: WV0125
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Boilers and HVAC Equipment
NAICS
n/a
SIC 3433: Heating Equipment, Except Electric and Warm Air Furnaces
Sales Range $10
M
to 50
M
# of Employees 188
Plant Area 190,000
ft2
Annual Production 15,000
ton
Production Hrs. Annual 4,862
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $103,547 3,039,566
kWh
Electricity Demand $83,724 8,782
kW-mo/yr
Electricity Fees $28,213 -
Natural Gas $120,537 45,955
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $278,083 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $50,912

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $11,488 $1,329 $5,204
60,082
kWh
$6,284
-
kW-mo/yr
- - - -
02 2.4133: Use most efficient type of electric motors $2,011 $2,499 $541
12,603
kWh
$1,470
-
kW-mo/yr
- - - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $191 $240 $191
4,396
kWh
- - - - -
04 2.4221: Install compressor air intakes in coolest locations $165 $168 $165
3,810
kWh
- - - - -
05 2.4314: Use synthetic lubricant $699 $351 $699
16,120
kWh
- - - - -
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $22,920 - - $22,920
-
kW-mo/yr
- - - -
07 2.2136: Install / repair insulation on steam lines $1,915 $1,809 - - $1,915
-
MMBtu
- - -
08 2.8123: Pay utility bills on time $2,478 - - - - - - $2,478
09 3.5248: Separate and recycle scrap metal to foundry or for sale $28,350 - - - - - - $28,350
10 3.4111: Use closed cycle process to minimize waste water production $86 $160 - - - $86
-
Tgal
- -
11 3.5315: Lease / purchase baler; sell cardboard to recycler $3,780 - - - - - - $3,780
12 4.423: Move product using mechanical means $204,000 $302,500 - - - - $204,000 -
TOTAL RECOMMENDED $278,083 $309,056 $6,800
97,011
kWh
$30,674
-
kW-mo/yr
$1,915
-
MMBtu
$86
-
Tgal
$204,000 $34,608
TOTAL IMPLEMENTED $50,912 $6,228 $6,635
93,201
kWh
$7,754
-
kW-mo/yr
$1,915
-
MMBtu
- - $34,608
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs