ITAC Assessment: WV0124
ITAC logo
ITAC Assessment: WV0124
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Burners
NAICS
n/a
SIC 3823: Industrial Instruments for Measurement, Display, and Control of Process Variables; and Related Products
Sales Range $10
M
to 50
M
# of Employees 135
Plant Area 118,773
ft2
Annual Production 2,000
pieces
Production Hrs. Annual 4,704
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $92,922 2,403,576
kWh
Electricity Demand $118,911 7,302
kW-mo/yr
Electricity Fees $(-7,046.0) -
Natural Gas $112,758 19,444
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $67,046 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,451

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,851 $361 $618
17,292
kWh
$1,233
-
kW-mo/yr
- - - - -
02 2.4133: Use most efficient type of electric motors $1,835 $1,740 $221
6,155
kWh
$1,614
-
kW-mo/yr
- - - - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $391 $1,080 $391
10,844
kWh
- - - - - -
04 2.4221: Install compressor air intakes in coolest locations $150 $290 $150
4,103
kWh
- - - - - -
05 2.6121: Reduce hot water temperature to the minimum required $5,413 - $5,413
151,524
kWh
- - - - - -
06 2.7314: Reduce ventilation air $7,818 $6,200 - - $7,818
-
MMBtu
- - - -
07 2.7491: Insulate glazing, walls, ceilings, and roofs $1,549 $3,268 - - $1,549
-
MMBtu
- - - -
08 2.6212: Turn off equipment during breaks, reduce operating time $11,865 - $288
7,913
kWh
- $11,577
-
MMBtu
- - - -
09 2.2437: Recover waste heat from equipment $1,276 $800 - - $1,276
-
MMBtu
- - - -
10 3.6193: Install equipment (eg compactor) to reduce disposal costs $3,097 $11,000 $(-13.0)
(-293)
kWh
- - $(-490.0) $3,600 - -
11 3.5315: Lease / purchase baler; sell cardboard to recycler $3,924 $10,000 $(-20.0)
(-586)
kWh
- - $(-980.0) $3,429 $1,495 -
12 3.4111: Use closed cycle process to minimize waste water production $7,143 $1,570 $(-1,257.0)
(-35,170)
kWh
- - - $8,400 - -
13 4.632: Change operating conditions $20,734 $5,000 $(-3,266.0)
(-91,442)
kWh
- - $(-48,000.0) - $(-48,000.0) $120,000
TOTAL RECOMMENDED $67,046 $41,309 $2,525
70,340
kWh
$2,847
-
kW-mo/yr
$22,220
-
MMBtu
$(-49,470.0) $15,429 $(-46,505.0) $120,000
TOTAL IMPLEMENTED $24,451 $10,951 $5,386
150,645
kWh
$2,847
-
kW-mo/yr
$7,818
-
MMBtu
- $8,400 - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs