ITAC Assessment: WV0123
ITAC logo
ITAC Assessment: WV0123
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Steel Rolls
NAICS
n/a
SIC 3325: Steel Foundries, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 103
Plant Area 217,000
ft2
Annual Production 5,000
pieces
Production Hrs. Annual 7,200
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,657,359 46,405,042
kWh
Electricity Demand $645,404 131,771
kW-mo/yr
Electricity Fees $54,054 -
Natural Gas $1,667,457 545,463
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,001,370 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $46,410

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Increase in Production Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $141 $127 $58
1,172
kWh
$83
-
kW-mo/yr
- - - - -
02 2.4133: Use most efficient type of electric motors $9,494 $27,687 $5,269
103,458
kWh
$4,225
-
kW-mo/yr
- - - - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,827 $920 $3,827
75,322
kWh
- - - - - -
04 2.4221: Install compressor air intakes in coolest locations $1,460 $280 $1,460
28,722
kWh
- - - - - -
05 2.7241: Install outside air damper / economizer on hvac unit $1,572 $1,500 $1,572
30,774
kWh
- - - - - -
06 2.2437: Recover waste heat from equipment $2,050 $910 - - $2,050
-
MMBtu
- - - -
07 2.2511: Insulate bare equipment $32,948 $910 - - $32,948
-
MMBtu
- - - -
08 2.3412: Use waste heat to produce steam to drive a steam turbine-generator $21,126 $43,250 $25,593
829,426
kWh
$1,533
-
kW-mo/yr
- - $(-6,000.0) - -
09 3.5315: Lease / purchase baler; sell cardboard to recycler $7,837 $9,000 $(-18.0)
(-293)
kWh
- - $(-1,250.0) $5,136 $3,969 -
10 3.6193: Install equipment (eg compactor) to reduce disposal costs $915 $5,000 - - - $(-625.0) $1,540 - -
11 4.111: Add equipment/ operators to reduce production bottleneck $920,000 $1,507,800 - - - - - - $920,000
TOTAL RECOMMENDED $1,001,370 $1,597,384 $37,761
1,068,581
kWh
$5,841
-
kW-mo/yr
$34,998
-
MMBtu
$(-1,875.0) $676 $3,969 $920,000
TOTAL IMPLEMENTED $46,410 $29,644 $9,154
179,952
kWh
$4,308
-
kW-mo/yr
$32,948
-
MMBtu
- - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs