ITAC Assessment: MS0399
ITAC logo
ITAC Assessment: MS0399
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Step drill bits, band saw blades, Custom printed safety vests
NAICS 333515: Cutting Tool and Machine Tool Accessory Manufacturing
SIC 3545: Cutting Tools, Machine Tool Accessories, and Machinists' Precision Measuring Devices
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 100,000
ft2
Annual Production 1,212,150
units
Production Hrs. Annual 8,760
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $402,755 8,030,484
kWh
Electricity Demand $85,248 14,508
kW-mo/yr
Electricity Fees $84,076 -
Natural Gas $2,374 158
MMBtu
Waste Disposal Costs
Water Usage $548 127
Tgal
TOTAL YEARLY COSTS $575,001
RECOMMENDED SAVINGS* $30,725 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $18,456 $31,953 $18,213
362,804
kWh
$244
-
kW-mo/yr
02 2.7135: Install occupancy sensors $4,013 $6,244 $3,813
75,956
kWh
$200
-
kW-mo/yr
03 2.2531: Re-size charging openings or add movable cover or door $8,256 - $7,760
154,574
kWh
$496
-
kW-mo/yr
TOTAL RECOMMENDED $30,725 $38,197 $29,785
593,334
kWh
$940
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs