Assessment Year | 2023 |
---|---|
Principal Product | Cement Backer Boards |
NAICS | 327420: Gypsum Product Manufacturing |
SIC | 3275: Gypsum Products |
Sales Range | $10 M to 50M |
# of Employees | 40 |
Plant Area |
350,000
ft2
|
Annual Production | 600,000,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $104,411 | 1,701,840 |
kWh
|
$0.061 |
Electricity Demand | $27,911 | 3,282 |
kW-mo/yr
|
$8.50 |
Electricity Fees | $118,982 | - |
|
- |
LPG | $149,305 | 612 |
MMBtu
|
$243.82 |
TOTAL YEARLY COSTS | $400,609 | |||
RECOMMENDED SAVINGS* | $277,823 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $184,809 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $74,653 | - | - | - | - | $74,653 | |
02 | 2.2442: Preheat combustion air with waste heat | $57,942 | $18,000 | - | - |
$57,942
-
MMBtu
|
- | |
03 | 2.3141: Use battery storage for demand control | $39,593 | $8,330 |
$(-305.0)
(-5,000)
kWh
|
$(-102.0)
-
kW-mo/yr
|
- | $40,000 | |
04 | 2.7243: Improve air circulation with destratification fans / other methods | $31,388 | $12,420 |
$(-357.0)
(-5,845)
kWh
|
$(-287.0)
-
kW-mo/yr
|
- | $32,032 | |
05 | 2.3191: Use demand controller or load shedder | $13,170 | $9,156 |
$10,381
170,184
kWh
|
$2,789
-
kW-mo/yr
|
- | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,242 | $9,619 |
$6,242
102,333
kWh
|
- | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,225 | $412 |
$6,225
102,053
kWh
|
- | - | - | |
08 | 2.4133: Use most efficient type of electric motors | $4,851 | $24,000 |
$3,469
56,873
kWh
|
$1,382
-
kW-mo/yr
|
- | - | |
09 | 2.1222: Install turbulators | $4,318 | $5,000 | - | - |
$4,318
-
MMBtu
|
- | |
10 | 4.424: Improve space comfort conditioning | $34,250 | $2,384 |
$(-527.0)
(-8,632)
kWh
|
$(-538.0)
-
kW-mo/yr
|
- | $35,315 | |
11 | 4.664: Level three - install or modify control system with communication and nonlocal external information (i.e. weather foreca | $5,191 | $11,500 |
$5,191
85,092
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $277,823 | $100,821 |
$30,319
497,058
kWh
|
$3,244
-
kW-mo/yr
|
$62,260
-
MMBtu
|
$182,000 | ||
TOTAL IMPLEMENTED | $184,809 | $80,165 |
$14,747
241,782
kWh
|
$455
-
kW-mo/yr
|
$62,260
-
MMBtu
|
$107,347 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs