| Assessment Year | 1997 |
|---|---|
| Principal Product | Vinyl and Aluminum Doors and Windows |
| NAICS |
n/a
|
| SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
| Sales Range | $10 M to 50M |
| # of Employees | 220 |
| Plant Area |
66,240
ft2
|
| Annual Production | 92,000
pieces
|
| Production Hrs. Annual | 2,385
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $72,768 | 757,034 |
kWh
|
$0.096 |
| Natural Gas | $41,228 | 10,221 |
MMBtu
|
$4.03 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $30,075 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $26,567 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $535 | $610 |
$535
5,569
kWh
|
- | - | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,026 | $200 |
$2,026
21,102
kWh
|
- | - | - | - | |
| 03 | 2.2437: Recover waste heat from equipment | $368 | $755 | - |
$368
-
MMBtu
|
- | - | - | |
| 04 | 2.2511: Insulate bare equipment | $890 | $1,440 | - |
$890
-
MMBtu
|
- | - | - | |
| 05 | 2.7243: Improve air circulation with destratification fans / other methods | $2,763 | $10,400 |
$(-224.0)
(-2,345)
kWh
|
$2,987
-
MMBtu
|
- | - | - | |
| 06 | 3.3122: Use filtration, centrifuging to remove contaminants | $2,250 | $4,720 |
$(-86.0)
(-879)
kWh
|
- |
$2,996
-
Tgal
|
$(-540.0) | $(-120.0) | |
| 07 | 3.4151: Minimize water usage | $2,043 | $2,000 | - |
$1,168
-
MMBtu
|
$875
-
Tgal
|
- | - | |
| 08 | 4.513: Re-arrange equipment layout to reduce labor costs | $19,200 | $1,700 | - | - | - | $19,200 | - | |
| TOTAL RECOMMENDED | $30,075 | $21,825 |
$2,251
23,447
kWh
|
$5,413
-
MMBtu
|
$3,871
-
Tgal
|
$18,660 | $(-120.0) | ||
| TOTAL IMPLEMENTED | $26,567 | $14,910 |
$2,337
24,326
kWh
|
$4,155
-
MMBtu
|
$875
-
Tgal
|
$19,200 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs