| Assessment Year | 1996 |
|---|---|
| Principal Product | Bread and Buns |
| NAICS |
n/a
|
| SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
| Sales Range | $10 M to 50M |
| # of Employees | 165 |
| Plant Area |
70,000
ft2
|
| Annual Production | 52,000,000
lb
|
| Production Hrs. Annual | 5,772
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $111,171 | 3,398,593 |
kWh
|
$0.033 |
| Electricity Fees | $49,555 | - |
|
- |
| Natural Gas | $157,395 | 32,993 |
MMBtu
|
$4.77 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $32,808 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $26,759 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $735 | $297 |
$735
21,395
kWh
|
- | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $516 | $2,274 |
$516
14,947
kWh
|
- | - | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $214 | $111 |
$214
6,155
kWh
|
- | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $685 | $100 |
$685
19,930
kWh
|
- | - | |
| 05 | 2.4314: Use synthetic lubricant | $558 | $720 |
$558
16,120
kWh
|
- | - | |
| 06 | 2.7241: Install outside air damper / economizer on hvac unit | $2,183 | $1,467 |
$2,183
63,306
kWh
|
- | - | |
| 07 | 2.2437: Recover waste heat from equipment | $2,485 | $480 | - |
$2,485
-
MMBtu
|
- | |
| 08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,392 | $1,000 | - |
$1,392
-
MMBtu
|
- | |
| 09 | 2.1213: Direct warmest air to combustion intake | $2,260 | $4,010 | - |
$2,260
-
MMBtu
|
- | |
| 10 | 3.5217: Reuse / recycle/ sell paper products | $21,780 | - | - | - | $21,780 | |
| TOTAL RECOMMENDED | $32,808 | $10,459 |
$4,891
141,853
kWh
|
$6,137
-
MMBtu
|
$21,780 | ||
| TOTAL IMPLEMENTED | $26,759 | $3,871 |
$2,494
72,392
kWh
|
$2,485
-
MMBtu
|
$21,780 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs