| Assessment Year | 1995 |
|---|---|
| Principal Product | Custom mixed rubber for molding and extrusions |
| NAICS |
n/a
|
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
90,000
ft2
|
| Annual Production | 38,000,000
lb
|
| Production Hrs. Annual | 7,956
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $415,676 | 7,538,101 |
kWh
|
$0.055 |
| Natural Gas | $126,609 | 36,238 |
MMBtu
|
$3.49 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $73,783 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $28,642 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,706 | $855 |
$3,706
123,095
kWh
|
- | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $7,349 | $22,310 |
$7,349
244,138
kWh
|
- | - | - | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $493 | $600 |
$493
16,413
kWh
|
- | - | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $5,722 | $378 |
$5,722
190,211
kWh
|
- | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,783 | $250 |
$3,783
125,733
kWh
|
- | - | - | |
| 06 | 2.2437: Recover waste heat from equipment | $2,194 | $1,085 | - |
$2,194
-
MMBtu
|
- | - | |
| 07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,005 | $500 | - |
$1,005
-
MMBtu
|
- | - | |
| 08 | 2.1213: Direct warmest air to combustion intake | $3,196 | $2,194 | - |
$3,196
-
MMBtu
|
- | - | |
| 09 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $10,573 | $4,300 | - |
$3,069
-
MMBtu
|
$7,504
-
Tgal
|
- | |
| 10 | 2.1123: Install automatic stack damper | $6,023 | $725 | - |
$6,023
-
MMBtu
|
- | - | |
| 11 | 2.1222: Install turbulators | $3,340 | $700 | - |
$3,340
-
MMBtu
|
- | - | |
| 12 | 2.2136: Install / repair insulation on steam lines | $323 | $415 | - |
$323
-
MMBtu
|
- | - | |
| 13 | 2.7221: Lower temperature during the winter season and vice-versa | $2,415 | $480 | - |
$2,415
-
MMBtu
|
- | - | |
| 14 | 2.7243: Improve air circulation with destratification fans / other methods | $5,140 | $2,400 | - |
$5,140
-
MMBtu
|
- | - | |
| 15 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $18,521 | - | - | - | - |
$18,521
-
lb
|
|
| TOTAL RECOMMENDED | $73,783 | $37,192 |
$21,053
699,590
kWh
|
$26,705
-
MMBtu
|
$7,504
-
Tgal
|
$18,521
-
lb
|
||
| TOTAL IMPLEMENTED | $28,642 | $29,210 |
$15,331
509,379
kWh
|
$5,807
-
MMBtu
|
$7,504
-
Tgal
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs