Assessment Year | 2007 |
---|---|
Principal Product | Aerospace structural components |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
150,000
ft2
|
Annual Production | 70,000
pieces
|
Production Hrs. Annual | 4,732
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $153,250 | 4,081,527 |
kWh
|
$0.038 |
Electricity Demand | $88,055 | 10,876 |
kW-mo/yr
|
$8.10 |
Natural Gas | $58,251 | 6,734 |
MMBtu
|
$8.65 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $164,435 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7425: Clean or color roof to reduce solar load | $144,120 | $500,000 |
$144,120
1,913,950
kWh
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,666 | $860 |
$9,666
128,367
kWh
|
- | |
03 | 2.2437: Recover waste heat from equipment | $8,334 | $7,480 | - |
$8,334
-
MMBtu
|
|
04 | 2.1321: Replace fossil fuel equipment with electrical equipment | $2,042 | $6,800 | - |
$2,042
-
MMBtu
|
|
05 | 2.6232: Install set-back timers | $273 | $248 | - |
$273
-
MMBtu
|
|
TOTAL RECOMMENDED | $164,435 | $515,388 |
$153,786
2,042,317
kWh
|
$10,649
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs