Assessment Year | 2001 |
---|---|
Principal Product | Mineral Sands |
NAICS |
n/a
|
SIC | 3295: Minerals and Earths, Ground or Otherwise Treated |
Sales Range | $10 M to 50M |
# of Employees | 42 |
Plant Area |
10,500
ft2
|
Annual Production | 100,000
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $468,881 | 16,566,008 |
kWh
|
$0.028 |
Electricity Demand | $85,976 | 27,541 |
kW-mo/yr
|
$3.12 |
Fuel Oil #6 | $356,937 | 72,779 |
MMBtu
|
$4.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $55,283 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $43,809 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #6 Savings | Solid Waste (haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $775 | $1,200 |
$672
24,002
kWh
|
$103
-
kW-mo/yr
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $706 | $410 |
$748
21,993
kWh
|
- | - | - | $(-42.0) | |
03 | 2.4133: Use most efficient type of electric motors | $13,613 | $64,742 |
$11,427
408,094
kWh
|
$2,186
-
kW-mo/yr
|
- | - | - | |
04 | 2.7131: Add area lighting switches | $2,086 | $2,358 |
$2,086
61,351
kWh
|
- | - | - | - | |
05 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $314 | $75 |
$314
11,213
kWh
|
- | - | - | - | |
06 | 2.2511: Insulate bare equipment | $20,239 | $2,500 | - | - |
$20,239
-
MMBtu
|
- | - | |
07 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $5,760 | $3,985 | - | - | - | - | $5,760 | |
08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $316 | $1,895 | - | - | - |
$316
-
lb
|
- | |
09 | 4.652: Replace existing equipment with more suitable substitutes | $10,697 | - |
$9,668
345,301
kWh
|
- | - | - | $1,029 | |
10 | 4.652: Replace existing equipment with more suitable substitutes | $777 | $525 |
$128
4,555
kWh
|
$19
-
kW-mo/yr
|
- | - | $630 | |
TOTAL RECOMMENDED | $55,283 | $77,690 |
$25,043
876,509
kWh
|
$2,308
-
kW-mo/yr
|
$20,239
-
MMBtu
|
$316
-
lb
|
$7,377 | ||
TOTAL IMPLEMENTED | $43,809 | $77,165 |
$15,247
526,653
kWh
|
$2,289
-
kW-mo/yr
|
$20,239
-
MMBtu
|
$316
-
lb
|
$5,718 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #6 Savings | Solid Waste (haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs