Assessment Year | 1995 |
---|---|
Principal Product | Blankets |
NAICS |
n/a
|
SIC | 2221: Broadwoven Fabric Mills, Manmade Fiber and Silk |
Sales Range | $10 M to 50M |
# of Employees | 325 |
Plant Area |
115,000
ft2
|
Annual Production | 3,000,000
pieces
|
Production Hrs. Annual | 7,344
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $241,361 | 4,811,841 |
kWh
|
$0.050 |
Natural Gas | $29,050 | 5,871 |
MMBtu
|
$4.95 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,070 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,305 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $176 | $320 |
$176
6,741
kWh
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $6,004 | $14,890 |
$6,004
230,363
kWh
|
- | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,940 | $1,560 |
$1,940
74,443
kWh
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $271 | $295 |
$271
5,862
kWh
|
- | |
05 | 2.7221: Lower temperature during the winter season and vice-versa | $1,589 | - |
$1,589
60,961
kWh
|
- | |
06 | 2.7241: Install outside air damper / economizer on hvac unit | $1,253 | $2,300 |
$1,253
48,066
kWh
|
- | |
07 | 2.1213: Direct warmest air to combustion intake | $643 | $1,566 | - |
$643
-
MMBtu
|
|
08 | 2.1123: Install automatic stack damper | $6,039 | $560 | - |
$6,039
-
MMBtu
|
|
09 | 2.2511: Insulate bare equipment | $155 | $171 | - |
$155
-
MMBtu
|
|
TOTAL RECOMMENDED | $18,070 | $21,662 |
$11,233
426,436
kWh
|
$6,837
-
MMBtu
|
||
TOTAL IMPLEMENTED | $16,305 | $21,342 |
$9,468
358,734
kWh
|
$6,837
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs