| Assessment Year | 1995 |
|---|---|
| Principal Product | Steel fabrication, forging, and rolling |
| NAICS |
n/a
|
| SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
| Sales Range | $10 M to 50M |
| # of Employees | 87 |
| Plant Area |
390,000
ft2
|
| Annual Production | 34,700,000
pieces
|
| Production Hrs. Annual | 8,000
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $342,722 | 7,213,951 |
kWh
|
$0.048 |
| Natural Gas | $798,477 | 253,722 |
MMBtu
|
$3.15 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $47,252 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,696 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7124: Make a practice of turning off lights when not needed | $694 | - |
$694
18,464
kWh
|
- | |
| 02 | 2.4226: Use / purchase optimum sized compressor | $38,326 | $36,000 |
$38,326
1,020,223
kWh
|
- | |
| 03 | 2.7291: Reschedule and rearrange multiple-source heating systems | $4,127 | $19 | - |
$4,127
-
MMBtu
|
|
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,409 | - |
$1,409
37,515
kWh
|
- | |
| 05 | 2.4314: Use synthetic lubricant | $2,696 | - |
$2,696
71,805
kWh
|
- | |
| TOTAL RECOMMENDED | $47,252 | $36,019 |
$43,125
1,148,007
kWh
|
$4,127
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $2,696 | - |
$2,696
71,805
kWh
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs