Assessment Year | 1994 |
---|---|
Principal Product | Truck hoods |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 303 |
Plant Area |
284,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 8,064
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $794,357 | 16,883,060 |
kWh
|
$0.047 |
Natural Gas | $349,177 | 92,484 |
MMBtu
|
$3.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $285,031 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $195,686 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,256 | $5,485 |
$2,256
85,287
kWh
|
- | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $298 | - |
$298
10,551
kWh
|
- | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $77,346 | $5,000 | - |
$77,346
-
MMBtu
|
|
04 | 2.7241: Install outside air damper / economizer on hvac unit | $15,913 | $8,987 |
$15,913
602,579
kWh
|
- | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $22,600 | $9,000 | - |
$22,600
-
MMBtu
|
|
06 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $47,244 | $1,200 | - |
$47,244
-
MMBtu
|
|
07 | 2.2136: Install / repair insulation on steam lines | $2,475 | $480 | - |
$2,475
-
MMBtu
|
|
08 | 2.2511: Insulate bare equipment | $2,225 | $569 | - |
$2,225
-
MMBtu
|
|
09 | 2.7261: Install timers and/or thermostats | $95,384 | $6,300 |
$95,384
4,248,535
kWh
|
- | |
10 | 2.2211: Use optimum temperature | $15,702 | $800 | - |
$15,702
-
MMBtu
|
|
11 | 2.4314: Use synthetic lubricant | $3,588 | - |
$3,588
135,991
kWh
|
- | |
TOTAL RECOMMENDED | $285,031 | $37,821 |
$117,439
5,082,943
kWh
|
$167,592
-
MMBtu
|
||
TOTAL IMPLEMENTED | $195,686 | $18,634 |
$97,938
4,344,373
kWh
|
$97,748
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs