ITAC Assessment: KU0353
ITAC logo
ITAC Assessment: KU0353
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product FISHING LURES (BAIT)
NAICS
n/a
SIC 3949: Sporting and Athletic Goods, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area
n/a
Annual Production 9,000,000
pieces
Production Hrs. Annual 4,160
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $42,284 708,382
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $34,296 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $34,296

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 4.221: Use only amount of packaging material necessary $26,522 - $122
2,052
kWh
$26,400
02 3.4115: Recover and reuse cooling water $603 - $(-35.0)
(-586)
kWh
$638
03 2.2437: Recover waste heat from equipment $2,291 $2,400 $2,291
38,394
kWh
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $752 $120 $752
12,603
kWh
-
05 2.4221: Install compressor air intakes in coolest locations $386 $420 $386
6,448
kWh
-
06 2.4239: Eliminate or reduce compressed air usage $315 $175 $315
5,275
kWh
-
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $297 $1,000 $297
4,982
kWh
-
08 2.6232: Install set-back timers $1,871 $300 $1,871
31,360
kWh
-
09 2.7421: Reduce glazed areas in buildings $1,259 $1,105 $1,259
21,102
kWh
-
TOTAL RECOMMENDED $34,296 $5,520 $7,258
121,630
kWh
$27,038
TOTAL IMPLEMENTED $34,296 $5,520 $7,258
121,630
kWh
$27,038
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs