ITAC Assessment: WV0019
ITAC logo
ITAC Assessment: WV0019
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Fiber glass topliners for automobiles
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 450
Plant Area 393,248
ft2
Annual Production 0
units
Production Hrs. Annual 8,736
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $816,204 37,451,935
kWh
Natural Gas $2,397,014 536,871
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,679 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,853 $15,942 $2,853
123,681
kWh
-
02 2.4133: Use most efficient type of electric motors $4,030 $96,730 $4,030
78,253
kWh
-
03 2.7111: Reduce illumination to minimum necessary levels $961 - $961
41,618
kWh
-
04 2.7447: Install vinyl strip / high speed / air curtain doors $11,716 $8,860 - $11,716
-
MMBtu
05 2.4314: Use synthetic lubricant $2,119 - $2,119
91,735
kWh
-
TOTAL RECOMMENDED $21,679 $121,532 $9,963
335,287
kWh
$11,716
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs